I <br /> City of Everett 00 72 00 - 48 <br /> I <br /> 12.4.3.3.1 Adjustment of Contract Sum <br /> The Contractor shall not be entitled to any adjustment in Contract Sum for Delays concurrently <br /> caused by the Owner and the Contractor. <br /> 12.4.3.3.2 Adjustment of Contract Time <br /> The Contractor shall be entitled to an extension of Contract Time for the Owner caused portion of any <br /> Delay concurrently caused by the Owner and Contractor to the extent the Owner caused the Delay to <br /> extend longer than if the Contractor had solely caused the Delay. <br /> 12.4.3.4 Third Party Caused Delays and Force Majeure <br /> For the purposes of this section 12.4.3.4,a"Force Majeure Event"is defined as earthquake,flood, <br /> pandemic(and governmental laws,regulations,requirements,and orders resulting therefrom),natural <br /> disasters,acts of war or acts of terrorism. Pandemic in the preceding sentence includes without <br /> limitation the COVID-19/novel coronavirus(SARS-CoV-2)pandemic,which is the subject of the <br /> Governor's proclamation dated February 29,2020, and subsequent proclamations. <br /> For the purposes of this section 12.4.3.4,a"Third Party"is defined as a third party for whom neither <br /> the Contractor nor the City is responsible. <br /> 12.4.3.4.1 Adjustment of Contract Sum ' <br /> The Owner and the Contractor shall not be responsible to compensate each other financially for <br /> any Delay to the extent caused by a Third Party or a Force Majeure Event. A Delay caused by a <br /> utility's failure to provide service or relocate its lines(despite a timely request for such service or <br /> relocation)is an example of this kind of Delay for which neither the Contractor nor the Owner is <br /> financially responsible to the other. Mislocated utility lines or utility lines not located are another <br /> example of a Delay for which neither the Contractor nor the Owner is responsible to the other. <br /> However,the Contractor's failure to request a utility locate or relocation in a timely way is not, <br /> and any resulting Delay would be the responsibility of the Contractor. Because the Contractor is <br /> responsible for ordering materials and Equipment,Contractor shall not be entitled to an <br /> adjustment of Contract Time or Contract Sum due to Delays caused by the lack of materials or <br /> Equipment. A strike,job action, slowdown,work to rule,or other job action or labor dispute or <br /> problem is not a Delay caused by a Third Party for the purposes of section 12.4.3 Delays. <br /> 12.4.3.4.2 Adjustment of Contract Time <br /> The Contractor shall be entitled to an extension of Contract Time for Delays to the extent caused <br /> used <br /> by a Third Party or Force Majeure Event. Extension of Contract Time shall be determined <br /> pursuant to 5.2.2.2 Extensions of Contract Time. <br /> 12.4.3.5 Extended or Unabsorbed Overhead <br /> 12.4.3.5.1 General <br /> To present a request for additional compensation for Extended or Unabsorbed Overhead,the <br /> Contractor has the burden of keeping and maintaining accurate documentation to support any such <br /> claim. If the Contractor fails to provide or keep adequate financial data for an accurate and fair <br /> Eichleay calculation,Contractor waives and releases any claim for Unabsorbed or Extended <br /> Overhead.In presenting any claim under this section of the Contract,the Contractor agrees to provide <br /> to the Owner any and all financial data needed by the Owner,or its representative,to review, <br /> substantiate and evaluate any claim for Extended and/or Unabsorbed Home Office Overhead. Failure <br /> to provide the requested information shall constitute waiver by the Contractor. <br /> If Contractor is entitled to an adjustment of Contract Sum for Unabsorbed or Extended Overhead,it <br /> shall be calculated as provided in 9.5.3. Unabsorbed and Extended Overhead. <br /> 12.4.3.5.2 Elements <br /> i <br /> 00 72 00 - 48 GENERAL CONDITIONS <br />