I <br /> City of Everett Inductive Charging Infrastructure for Field Installation 01 26 00 - 1 <br /> 111 <br /> I <br /> SECTION 01 26 00 -CONTRACT MODIFICATION PROCEDURES <br /> PART 1 - GENERAL i <br /> I <br /> 1.1 SUMMARY OF MODIFICATIONS PROCEDURES <br /> IA. Changes to the Work may be required due to field conditions, requests made by the <br /> Owner, clarifications to the bid documents, or other needs that result in a change in the <br /> cost of the work and/or change in the number of contract days per 00 72 00-6. The <br /> I changes to the work will be tracked individually as Request for Change Proposals <br /> (RFCP.). Request for Change Proposals may either be prepared as a Field Directive, or <br /> as a request for pricing prior to proceeding with the work. <br /> IB. A change order will be issued for one or more RFCP's grouped into a single change <br /> order. Payment for changed work cannot be paid until the change order is finalized, and <br /> Iapproved as outlined per 00 72 00 6.3. <br /> C. The Request for Change Proposal shall clearly identify all labor, material, equipment, <br /> incidentals, including subcontractor's and supplier's invoices or quotes and Contractor's <br /> I timecards. A reference from the latest approved schedule shall be attached justifying <br /> any time extension request. Mark ups for all overhead, profit, bond cost, B & 0 taxes, <br /> and insurance shall be added per 00 72 00. The form included at the end of this section <br /> Iwill be used for directing the work to be done in one of the two manners described below. <br /> D. Contractor, and Subcontractors where required, shall provide a breakdown of labor costs <br /> I <br /> including basic wage rates, fringe benefits, FICA, FUTA and SUCA add-ons, per 00 72 <br /> 00 9.6. Where premium time is involved, the Contractor shall provide a breakdown of <br /> costs in the same detail. <br /> I1.2 FIELD DIRECTIVE MODIFICATION PROPOSALS <br /> I A. Changed conditions and/or unanticipated circumstances may require immediate <br /> revisions to Work which are essential and from which a delay would result in a time and <br /> or cost penalty to the project. When such a condition exists, the Owner shall issue a <br /> written Field Directive to the Contractor. <br /> IB. The Owner will provide direction for the Contractor identifying the necessary changes to <br /> be made. The Field Directive shall be identified with a Request for Change number. The <br /> I <br /> Contractor will provide pricing per 1.01 C of this section within 15 days of the completion <br /> of the work. <br /> 1.3 LUMP SUM MODIFICATION PROPOSALS <br /> A. The Owner may request priced proposals which either add or delete work prior to <br /> Iproceeding with any changes. <br /> I01 26 00 - 1 CONTRACT MODIFICATION PROCEDURES <br />