Amendment 1 PSA with Brown and Caldwell for Port Gardner Storage Facility Project <br />Exhibit A Scope of Work <br />3 <br />− Unless otherwise specified, meetings and workshops will be held virtually. <br />− Construction period services begin with bid opening and conclude with final acceptance of <br />the work by the City. <br />− Services during contractor’s general warranty/guarantee period are not included. <br />− City PM will provide timely, consolidated staff review comments on draft work products. City <br />review periods will be identified in project schedules. <br />− Owner’s Representatives include BC, its subconsultants, City staff, and City’s 3rd party CM <br />firm that represent Owner’s interests in the Construction Contract that are employed or <br />retained by the Owner. <br />− Mileage for in person meetings and site visits are budgeted assuming the visits are to the <br />Port Gardner site. <br />− Meeting agendas and notes will be prepared by BC unless otherwise stated. <br />− The City will provide any available plans, construction records, asset information, operational <br />data, and related information that was not provided during development of the PGSF <br />preliminary design and provide access to plant staff for workshops and interviews. <br />− Past studies and reports, including condition assessments, form the basis upon which this <br />scope of work has been planned. Additional condition assessment will be performed during <br />demolition package construction. Discovery of new, unforeseeable, or latent issues <br />associated with the existing site and facilities may result in need for project plan, scope, and <br />budget changes. <br />− Existing site structures identified as remaining in the preliminary design are assumed to be <br />salvageable in their current form without foundation improvements or major structural <br />modifications and support. <br />− For budgeting purposes, it’s assumed the milestone schedule events will be as stated herein, <br />with Amendment 1 period from August 2023 through December 31, 2027 (53 calendar <br />months). <br />− Labor and expense effort is inflated at 5% per annum for work taking place after 2023. <br />− Work extent and sequence: The scope of work and budget allocation to each phase and task <br />is based on a number of assumptions regarding how the work is envisioned to proceed. <br />Given the nature of design work and services during construction, the actual level of effort <br />required for each phase/task may require reallocation of funds from one phase/task to <br />another. <br />• Construction cost estimates will be prepared to industry standards but will be subject to many <br />influences including, but not limited to, price of labor and materials, schedule impacts, unknown <br />or latent conditions of existing equipment or structures, and time or quality of performance by <br />others. These types of issues are difficult to forecast and are out of the control of BC and that <br />actual costs may vary substantially from the estimates prepared by BC. BC is therefore unable to <br />guarantee the accuracy of opinion of probable construction costs beyond that of industry <br />standards. <br />• Phase 670 Services During Construction for the Storage Facility Package were scoped and <br />budgeted based on the project definition available at preliminary (30%) design. Scope and <br />budget assumptions will be verified following Storage Facility Package final design and may differ <br />from those provided herein. The City will provide an opportunity for adjustment for scope and <br />budget shortfalls and/or overages based on the actual Storage Facility design prior to <br />construction contract award.