0 01 <br />Step 6. Flow Control <br />All projects triggering the flow control thresholds shall employ flow control BMPs to infiltrate, <br />disperse or detain stormwater runoff on -site to meet the flow control requirements of section 6.10 <br />of the DCSS. Projects that create 2,000 sf or more of net new impervious area shall provide flow <br />control designed by an Engineer. Use of the sizing tables below will not be allowed for projects <br />with 2,000 sf or more net new impervious area. <br />The three options for meeting the flow control requirement include dispersion, infiltration <br />(infiltration trench or bioretention) and detention. <br />Flow Control BMP Selection <br />Identify (check box of) the BMP that will be used to meet the flow control requirement <br />in the table below. All BMP's shall be designed to meet the flow requirements of <br />Section 6.10 of the DCSS. <br />Table 1. Flow Control BMP Selection <br />Opdon <br />Type <br />DCSS Design <br />2019 SWMMWW <br />Requirement <br />Design Guidance: <br />Sections: <br />p <br />I. <br />Downspout <br />BMP T5.106: <br />Dispersion <br />OR <br />System* <br />BMP 5.30: <br />❑ <br />2A <br />Infiltration <br />4-4.3 (2) <br />BMP T5.10A: <br />Trench <br />4-4.3 (4) <br />BMPT7.30: <br />❑ <br />2B. <br />Rain Gardens <br />Bioretention <br />COE Standard Plan <br />See Figure V-5.12 <br />Cells and Swales <br />426 <br />❑ <br />3. <br />Detention <br />Section 4-4.4 <br />BMP D.2 <br />(2), and 4-4.4 <br />or BMP D.3 <br />(3) <br />See Figure V12.1 <br />COE <br />Standard <br />Plans 415-418 <br />*For roof runoff only. To provide flow control from other surfaces, use option 2 or 3. <br />All facilities shall meet the facility access requirements of section 4-4.2, and Maintenance requirements of <br />section 4-4.2 (5) of Volume 1 of the DCSS. <br />City of Everett Public Works <br />Small Project Stormwater Site Plan Report for Projects in 15 <br />the Combined Sewer Area -April 2021 <br />