PROJECT: City of Everett <br />WFP EMERGENCY GENERATOR REPLACEMENT WO No. 3587 <br /> <br />WORK CHANGE DIRECTIVE – No. 004 <br />DATE OF ISSUANCE: JANUARY 9, 2023 <br /> <br />You are directed to proceed promptly with the following change (s): <br /> <br />Description: Revise the layout and dimensions of the Location 2 containment trench and <br />generator equipment pad. <br /> <br />Payment shall be tracked on a time and material basis and billed to Bid Item No. 20, Force <br />Account. <br /> <br />Purpose of WCD-004: The generator’s fuel supply and return lines are installed in the <br />containment trench. The per plan routing would cause too much back pressure for the fuel <br />return pump, resulting in blown seals. The containment trench routing was revised to shorten <br />the length of the fuel lines. <br />Attachments: WCDS 1 <br /> <br /> <br />If a claim is made that the above change(s) have affected Contract Price or Contract Times, any <br />claim for a Change Order based thereon will involve one or more of the following methods of <br />determining the effect of the change(s). <br /> <br />Method of determining change Method of determining change <br />In Contract Price: in Contract Times: <br /> <br /> Lump Sum Contractor’s records <br /> <br /> Time and Material Engineer’s records <br /> <br /> Other - Other <br /> <br /> <br />Estimated increase (decrease) in Contract Price: Estimated increase (decrease) in Contract Times: <br />$5,000.00 Substantial Completion 2 days: <br />If the change involves an increase, the Ready for final payment 2 days: <br />estimated amount is not to be exceeded If the change involves an increase, the <br />estimated without further authorization. times are not to be exceeded without further authorization. <br /> <br /> <br />ACCEPTED: IMCO General Construction AUTHORIZED: City of Everett <br /> <br />By: Date: By: Date: (Authorized Signature) (Authorized Signature) <br />Page 1 of 1