<br /> <br />Category 2: Sensitive information <br />Category 2: For official use only / disclosure permissible by law. <br />PROJECT: City of Everett <br />WFP EMERGENCY GENERATOR REPLACEMENT WO No. 3587 <br /> <br />WORK CHANGE DIRECTIVE – No. 009 Rev 01 <br />DATE OF ISSUANCE: October 17, 2023 <br /> <br />You are directed to proceed promptly with the following change (s): <br /> <br />Description: Provide additional power studies, as directed by the owner. One power study <br />shall remove the Backwash Pump Station and the existing generator at Location 2 from the <br />study. This study will evaluate powering the plant from the generator at Location 1. As part of <br />the study revise the Location 2 MCC bus bracing to an AIC rating of 65kA. <br />In an additional power study, revise the AIC rating of the Location 2 pump motor breakers and <br />the FWPS 1 feed breaker to and AIC rating of 65kA. <br />Per Sazan’s review comments for Submittal 041.2, provide torque control settings for the SEL- <br />751 relays. <br /> <br />Purpose of WCD-009: Additional power studies are necessary to evaluate if the Location 1 <br />generator can provide backup power for the plant, if the Backwash Pump Station is removed <br />from the grid and powered by its own generator. <br />Providing torque control settings for the City provided SEL-751 relays is not addressed in the <br />project specifications. <br /> <br />If a claim is made that the above change(s) have affected Contract Price or Contract Times, any <br />claim for a Change Order based thereon will involve one or more of the following methods of <br />determining the effect of the change(s). <br /> <br />Method of determining change Method of determining change <br />In Contract Price: in Contract Times: <br /> <br /> Lump Sum Contractor’s records <br /> <br /> Time and Material Engineer’s records <br /> <br /> Other - Other <br /> <br /> <br />Estimated increase (decrease) in Contract Price: Estimated increase (decrease) in Contract Times: <br />$11,826.27 Substantial Completion 0 days: <br />If the change involves an increase, the Ready for final payment 0 days: <br />estimated amount is not to be exceeded If the change involves an increase, the <br />estimated without further authorization. times are not to be exceeded without further authorization. <br /> <br /> <br />ACCEPTED: IMCO General Construction AUTHORIZED: City of Everett <br /> <br />By: Date: By: Date: (Authorized Signature) (Authorized Signature) <br />