Laserfiche WebLink
2024 Pavement Maintenance Overlay SPECIAL PROVISIONS PW# 3823 14 Contractor, take whatever steps are necessary to correct those deficiencies pursuant to 1 Section 1-05.7. 2 The Contractor will not be allowed an extension of contract time because of a delay in 3 the performance of the work attributable to the exercise of the Engineer’s right 4 hereunder. 5 6 Upon correction of all deficiencies, the Engineer will notify the Contractor and the 7 Contracting Agency, in writing, of the date upon which the work was considered physically 8 complete. That date shall constitute the Physical Completion Date of the contract, but shall 9 not imply acceptance of the work or that all the obligations of the Contractor under the 10 contract have been fulfilled. 11 12 1-05.11(3) Operational Testing 13 14 It is the intent of the Contracting Agency to have at the Physical Completion Date a 15 complete and operable system. Therefore when the work involves the installation of 16 machinery or other mechanical equipment; street lighting, electrical distribution or signal 17 systems; irrigation systems; buildings; or other similar work it may be desirable for the 18 Engineer to have the Contractor operate and test the work for a period of time after final 19 inspection but prior to the physical completion date. Whenever items of work are listed in 20 the Contract Provisions for operational testing they shall be fully tested under operating 21 conditions for the time period specified to ensure their acceptability prior to the Physical 22 Completion Date. During and following the test period, the Contractor shall correct any 23 items of workmanship, materials, or equipment which prove faulty, or that are not in first 24 class operating condition. Equipment, electrical controls, meters, or other devices and 25 equipment to be tested during this period shall be tested under the observation of the 26 Engineer, so that the Engineer may determine their suitability for the purpose for which 27 they were installed. The Physical Completion Date cannot be established until testing 28 and corrections have been completed to the satisfaction of the Engineer. 29 30 The costs for power, gas, labor, material, supplies, and everything else needed to 31 successfully complete operational testing, shall be included in the unit contract prices 32 related to the system being tested, unless specifically set forth otherwise in the proposal. 33 34 Operational and test periods, when required by the Engineer, shall not affect a 35 manufacturer’s guaranties or warranties furnished under the terms of the contract. 36 37 38 1-05.13.RTF 39 1-05.13 Superintendents, Labor and Equipment of Contractor 40 (August 14, 2013 APWA GSP) 41 42 Delete the sixth and seventh paragraphs of this section. 43 44 1-05.14.GR1 45 Cooperation with Other Contractors 46 47 1-05.14.INST1.GR1 48 Section 1-05.14 is supplemented with the following: 49