Laserfiche WebLink
CITY OF EVERETT SPECIAL PROVISIONS <br /> <br />Water Main Replacement “Y” – Ph 1 Div 1 – GENERAL REQMTS March 2024 <br />Work Order No. UP 3814 SP-116 <br />critical path method. This analysis shall include an updated schedule, an as-planned <br />schedule, an as-built schedule, a but-for schedule, and narrative explaining the alleged <br />causes, schedule impacts and all costs related to or arising out of the proposed <br />extension. Any requests for extensions of Contract Time by the Contractor shall be <br />submitted in accordance with these Contract Documents. If a request combined with <br />previous extension requests, equals 20 percent or more of the original Contract Time <br />then the Contractor’s letter of request must bear consent of Surety if so required by the <br />City. Extensions of Contract Time will be granted only as provided in the Contract <br />Documents and to the extent that affected critical activities exceed the Total Float time <br />along the affected paths of the reviewed Preliminary Schedule at the time the change <br />was authorized in writing by the City. Contractor has the burden of clearly and <br />convincingly demonstrating entitlement to any adjustment of Contract Time. <br />If the City is solely responsible for any Delay to Substantial Completion, Physical <br />Completion, Completion Date, or Final Acceptance, the Contractor shall only be entitled <br />to compensation or other damages as described in 1-09.11A REMEDIES, provided that <br />Contractor timely gave Notice pursuant to 1-04.5 NOTICE BY CONTRACTOR, timely <br />submitted a Contract Claim pursuant to 1-09.11(2) CONTRACT CLAIMS and fulfilled the <br />requirements of 1-08.3 PROGRESS SCHEDULE. <br />1-08.9 Liquidated Damages <br />Revise the second and third paragraphs of 1-08.9 to read as follows: <br /> <br />Accordingly, the Contractor agrees: <br />1. To pay (according to the following formula) liquidated damages for each <br />working day beyond the number of working days established for Physical <br />Completion, and <br />2. To authorize the Engineer to deduct these liquidated damages from any <br />money due or coming due to the Contractor. <br /> <br />Liquidated Damages Formula <br /> <br />LD=0.15C/T <br /> <br />Where: <br /> LD = liquidated damages per working day (rounded to the nearest dollar) <br /> C = original Contract amount <br /> T = original time for Physical Completion <br />When the Contract Work has progressed to Substantial Completion as defined in the <br />Contract, the Engineer may determine that the work is Substantially Complete. The <br />Engineer will notify the Contractor in writing of the Substantial Completion Date. For <br />overruns in Contract time occurring after the date so established, the formula for <br />liquidated damages shown above will not apply. For overruns in Contract time <br />occurring after the Substantial Completion Date, liquidated damages shall be assessed <br />on the basis of direct engineering and related costs assignable to the project until the <br />actual Physical Completion Date of all the Contract Work. The Contractor shall <br />complete the remaining Work as promptly as possible. Upon request by the Project <br />Engineer, the Contractor shall furnish a written schedule for completing the physical <br />Work on the Contract.