Laserfiche WebLink
5. General and administrative Overhead in an amount to be agreed upon, but not to exceed three <br />percent (3%) of original Contract Sum divided by the Contract Time for each day of the Delay. <br />Owner shall not owe Contractor compensation for extended Overhead or other delay costs to the <br />extent Contractor or anyone other than the City contributed to or is concurrently responsible for the <br />Delay. <br />12.4.3.1.2 Adjustment of Contract Time <br />If the Contractor is entitled to an adjustment of Contract Time because of a Delay solely caused by <br />the Owner that does not relate to Extra Work, Contractor shall be entitled to an adjustment of <br />Contract Time to the extent the Delay increases the duration of the Project, as measured by the critical <br />path and as demonstrated pursuant to the requirements of 5.2.2.2 Extensions of Contract Time. <br />12.4.3.2 Contractor Caused Delay <br />If the Contractor is solely responsible for any Delay to any interim milestone, Substantial Completion, <br />Physical Completion or the Completion Date, the Owner shall be entitled to liquidated or other damages <br />as provided elsewhere in the Contract Documents. The Contractor accepts the risk of any Delays caused <br />by strikes, work slowdowns, job actions and labor unrest of any kind. Contractor shall not be entitled to <br />any increase in Contract Sum or Contract Time due to a Delay it caused. <br />12.4.3.3 Delays Concurrently Caused by Contractor and Owner <br />If the Owner and the Contractor cause a Delay concurrently, neither the Owner nor the Contractor shall be <br />liable to the other except as provided herein. <br />12.4.3.3.1 Adjustment of Contract Sum <br />The Contractor shall not be entitled to any adjustment in Contract Sum for Delays concurrently <br />caused by the Owner and the Contractor. <br />12.4.3.3.2 Adjustment of Contract Time <br />The Contractor shall be entitled to an extension of Contract Time for the Owner caused portion of any <br />Delay concurrently caused by the Owner and Contractor to the extent the Owner caused the Delay to <br />extend longer than if the Contractor had solely caused the Delay. <br />12.4.3.4 Third Party Caused Delays and Force Majeure <br />For the purposes of this section 12.4.3.4, a "Force Majeure Event" is defined as earthquake, flood, <br />(and governmental laws, regulations, requirements, and orders resulting therefrom), natural disasters, <br />acts of war or acts of terrorism. <br />For the purposes of this section 12.4.3.4, a "Third Party" is defined as a third party for whom neither <br />the Contractor nor the City is responsible. <br />12.4.3.4.1 Adjustment of Contract Sum <br />The Owner and the Contractor shall not be responsible to compensate each other financially for <br />any Delay to the extent caused by a Third Party or a Force Majeure Event. A Delay caused by a <br />utility's failure to provide service or relocate its lines (despite a timely request for such service or <br />relocation) is an example of this kind of Delay for which neither the Contractor nor the Owner is <br />financially responsible to the other. Mislocated utility lines or utility lines not located are another <br />example of a Delay for which neither the Contractor nor the Owner is responsible to the other. <br />However, the Contractor's failure to request a utility locate or relocation in a timely way is not, <br />and any resulting Delay would be the responsibility of the Contractor. Because the Contractor is <br />responsible for ordering materials and Equipment, Contractor shall not be entitled to an <br />adjustment of Contract Time or Contract Sum due to Delays caused by the lack of materials or <br />Equipment. A strike, job action, slowdown, work to rule, or other job action or labor dispute or <br />problem is not a Delay caused by a Third Party for the purposes of section 12.4.3 Delays. <br />12.4.3.4.2 Adjustment of Contract Time <br />Reservoir 3 Replacement Phase 1 <br />Work Order No. UP3739 00 72 00 <br />GENERAL CONDITIONS March 2024 <br />