Laserfiche WebLink
City of Everett 01 32 16 - 2 <br /> <br /> <br />01 32 16 - 2 CONSTRUCTION PROGRESS SCHEDULE <br /> <br />B. Schedule shall be submitted electronic. Acceptable format .mmp or as otherwise <br />approved by Owner. <br />C. Review by the Owner or Owner’s Representative shall not constitute approval or <br />acceptance of the Contractor's construction means, methods, sequencing, logic, order, <br />precedence and succession of activities or Contractor’s ability to complete the Work in a <br />timely manner. <br />D. The review/approval of any schedule shall not transfer any of the Contractor’s <br />responsibilities to the Owner. <br />E. Subcontractors shall review all schedules prior to submittal. At the Owner’s option and <br />sole discretion, Owner may require Contractor to obtain written acceptance of each <br />schedule by subcontractors as practical and feasible, as the schedule relates to <br />subcontractors’ work. <br />1.4 UPDATES <br />A. The Project Construction Schedule will be reviewed and updated at each progress <br />meeting. All changes to the project schedule of more than three (3) working days shall <br />be documented. The Schedule shall be updated to show measures required to bring <br />project back on schedule. The Contractor alone shall remain responsible for adjusting <br />forces, equipment, and work schedules to ensure completion of the work within the <br />Contract Time. Any mistakes or errors in any schedule, including, but not limited to, <br />mistakes or errors of logic, order, precedence, and duration, are and remain the <br />Contractor's. <br />B. Should any activity not be completed by the stated scheduled date, the Owner will have <br />the right to require the Contractor to expedite completion of the activity by whatever <br />means appropriate and necessary, without additional compensation to the Contractor. <br />C. The Schedule shall be used to justify time extension days requested by the Contractor. <br />For additional days requested, the Schedule shall be detailed enough to identify the work <br />item(s) affected and the relationship to the changed or added work. <br />D. Schedule shall be provided during the construction meetings. Schedule shall be on <br />11x17 paper or as otherwise approved by Owner and shall show current work progress. <br />1.5 OWNER PROVIDED MATERIALS <br />A. All items to be provided by the Owner shall be incorporated into the schedule. The <br />schedule shall show when the materials are required to be delivered to the project and <br />when the materials will be installed. These materials are to be included in the preliminary <br />schedule, upon review; owner will confirm lead time for materials and delivery dates. <br />B. Contractor failure to include owner provided materials into the schedule shall be <br />responsible for all delays to the work or failure to notify the owner of tasks dependent <br />upon the owner furnished materials shall constitute a waiver by the contractor of any