Laserfiche WebLink
City of Everett 01 33 00 - 2 <br /> <br /> <br />01 33 00 - 2 SUBMITTAL PROCEDURES <br /> <br />B. The Contractor is required to review and approve all shop drawings prior to submitting <br />to Owner for review. All shop drawings received by Owner shall bear the Contractors <br />stamp of approval. <br />C. The Contractor shall provide the number of copies required for use by the contractor plus <br />three (3) additional copies to be retained by the Owner for all items of work as requested <br />by Owner or as required by the contract documents. The Owner or designee shall review <br />and return all shop drawings to the Contractor within the specified time but no later than <br />twenty (20) working days of receipt. The review of the shop drawings by the Owner or <br />designee is for the limited purpose of checking for conformance with the design concept <br />as expressed in the Contract documents. The review of shop drawings by the Owner <br />and/or Architect/Engineer is not conducted for the purpose of determining the accuracy <br />and completeness of other details such as dimensions, quantities, installation <br />instructions, or equipment performance, all of which remain the responsibility of the <br />Contractor. Approval of the shop drawings shall not release the Contractor from <br />responsibility for deviations from the contract documents. The approval of any shop <br />drawings that substantially deviates from the requirements of the contract documents <br />shall be evidenced by change order. <br />2.2 SAMPLES <br />A. Unless otherwise specifically directed by the Architect/Engineer, all samples shall be of <br />the precise article proposed to be furnished. <br />B. Submit the number of samples that are required to be returned plus two (2) that will be <br />retained by the Architect/Engineer. <br />2.3 <br />PART 3 - EXECUTION <br />3.1 IDENTIFICATION OF SUBMITTALS <br />A. Consecutively number all submittals. Accompany each submittal with a letter of <br />transmittal showing the transmittal number, date of transmittal, specifications section or <br />drawing number to which the submittal pertains, brief description of the material <br />submitted, and the company name of the originator of the submittal. <br />B. Maintain an accurate submittal log for the duration of the construction period, showing <br />status of all submittals. Make the log available to the Architect/Engineer upon request. <br />3.2 COORDINATION OF SUBMITTALS <br />A. Prior to submittal for Architect/Engineer’s review, use all means necessary to fully <br />coordinate all material, including the following: <br />1. Determine and verify all field dimensions and conditions.