Laserfiche WebLink
Section 00 72 00 GENERAL CONDITIONS <br /> <br />City of Everett 00 72 00-18 June 2024 <br />WFP Air Scour Blower Building Replacement Issued for Bid <br />UP3813 <br />activities. Contractor shall not attempt to “grab the Float” or make any effort to use any Float in <br />the Progress Schedule for the benefit of the Contractor. <br />Contractor shall submit with each Application for Payment or progress pay estimate an updated <br />Progress Schedule, but no less often than monthly. If requested by the Owner’s Representative <br />or the Owner, Contractor shall prepare and submit updated Progress Schedules from time to <br />time, which may be more frequent than monthly. <br />The Contractor hereby expressly agrees and acknowledges that any failure by Contractor to <br />provide accurate, complete, current and updated schedules with each and every progress pay <br />estimate or Application for Payment constitutes a waiver of any and all claims or requests for <br />adjustment of Contract Sum or Time that arise out of, result from, or are caused by, any Delay <br />on the Project or scheduling of the Work. Timely submission of monthly updated schedules is a <br />condition precedent to any later or subsequent Contract Claim or request for an adjustment of <br />either Contract Sum or Time related to or arising out of time, an alleged Delay, or the schedule <br />or sequence of Work. Similarly, the parties agree the Owner may withhold progress pay <br />estimates if updated schedules are not timely submitted. These remedies are cumulative and <br />not exclusive of any other remedy. The Owner’s use of one or more of these remedies does not <br />constitute an election or prevent the Owner from pursuing other remedies for this or other <br />defaults. <br />The Owner’s Representative’s review of any schedule shall not transfer any of the Contractor’s <br />responsibilities to the Owner. The Contractor alone shall remain responsible for adjusting <br />forces, equipment, and work schedules to ensure completion of the Work within the Contract <br />Time. Review by the Owner or Owner’s Representative shall not constitute approval or <br />acceptance of the Contractor's construction means, methods, sequencing, logic, order, <br />precedence and succession of activities or Contractor’s ability to complete the Work in a timely <br />manner. Any mistakes or errors in any schedule, including, but not limited to, mistakes or errors <br />of logic, order, precedence, and duration, are and remain the Contractor's. The Owner or <br />Owner’s Representative may comment upon the schedule. <br />5.2.2.2 Extensions of Contract Time <br />Any requests for extensions in Contract Time, whether resulting from Extra Work directed by the <br />Owner or not, shall be accompanied by an analysis of schedules using the critical path method. <br />This analysis shall include an updated schedule, an as-planned schedule, an as-built schedule, <br />a but-for schedule, and narrative explaining the alleged causes, schedule impacts and all costs <br />related to or arising out of the proposed extension. Any requests for extensions of Contract <br />Time by the Contractor shall be submitted in accordance with these General Conditions. <br />Extensions of Contract Time will be granted only as provided in the General Conditions and to <br />the extent that affected critical activities exceed the Total Float time along the affected paths of <br />the reviewed Preliminary Schedule at the time the change was authorized in writing by the <br />Owner. Contractor has the burden of clearly and convincingly demonstrating entitlement to any <br />adjustment of Contract Time. <br />If the Owner is solely responsible for any Delay to Substantial Completion, Physical Completion, <br />Completion Date, or Final Acceptance, the Contractor shall only be entitled to compensation or <br />other damages as described in 12.4 REMEDIES, provided that Contractor timely gave Notice <br />pursuant to ARTICLE 10. NOTICE TO OWNER, timely submitted a Contract Claim pursuant to <br />ARTICLE 12. CONTRACT CLAIMS and fulfilled the requirements of 5.2.2. Construction <br />Schedule. <br />5.2.3. Construction Progress <br />The Contractor shall furnish all labor, materials, facilities and Equipment necessary to insure the <br />prosecution and completion of the Project within the interim milestones, Substantial Completion, <br />Physical Completion and Completion Dates of the Contract. If Work falls seven (7) days or more