Section 00 72 00 GENERAL CONDITIONS <br /> <br />City of Everett 00 72 00-17 June 2024 <br />WFP Air Scour Blower Building Replacement Issued for Bid <br />UP3813 <br />Contract Time starts upon the later of the issuance of the Notice to Proceed or a date specified <br />in the Notice to Proceed. The Contractor shall promptly start the Work as soon as possible after <br />the date of the Notice to Proceed and shall prosecute the Work so that the various portions of <br />the Project shall be completed in accordance with the Contract Time period. Contractor shall <br />perform its work at such times and in such ways that the Work is not damaged by weather such <br />as wind, rain, or snow. Contractor shall correct or repair at its sole expense any Work damaged <br />by weather, irrespective of whether such damage is covered by insurance. No portions of the <br />Work where acceptable quality will be affected shall be constructed while unfavorable conditions <br />exist. By bidding on the Project and executing a Contract to perform the Work, Contractor <br />agrees the contractually required completion dates are feasible, reasonable, and achievable for <br />the Contract Sum. Contractor represents that it has considered all factors relevant to its price <br />and achieving the Completion Dates, including, but not limited to, weather, Site access, labor <br />conditions and the availability of materials, supplies and Equipment. Compliance with ARTICLE <br />10. NOTICE TO OWNER, ARTICLE 12. CONTRACT CLAIMS, and 5.2.2. Construction <br />Schedule are conditions precedent to a request for, consideration of, and grant of, any <br />extension of Contract Time. Failure to request a time extension in the manner and in the time <br />required by this section, and the Specifications referred to herein, constitutes a waiver by the <br />Contractor of any and all entitlement to an extension of time and any adjustment of Contract <br />Sum arising out, or related to, such Delay. <br />5.2.2. Construction Schedule <br />5.2.2.1 General <br />Contractor shall submit, update and maintain schedules as required by the Contract <br />Documents. <br />The Contractor shall provide sufficient material, equipment, and labor to meet the interim <br />milestones, Substantial Completion, Physical Completion and Completion Dates provided by the <br />Contract Documents. The Owner allocates its resources to a Contract based on the total time <br />allowed in the Contract. The Contractor may submit a schedule indicating Completion Date <br />earlier than the end of Contract Time, but Owner cannot guarantee its resources will be <br />available to meet such schedule. Owner shall not pay or be liable for any additional <br />compensation if the Contractor is not able to meet a schedule that indicates a Completion Date <br />earlier than the end of Contract Time. <br />Failure to schedule Owner furnished or installed materials and Equipment for installation on or <br />after its planned arrival pursuant to the Owner’s contract with the supplier or failure to Notify the <br />Owner of tasks dependent upon the fact or date of arrival of such Owner furnished materials <br />and Equipment, constitute a waiver by Contractor of any Contract Claim arising out of or related <br />to the timeliness of the furnishing or installation of such material and Equipment. All schedules <br />must allow for timely incorporation of any other's work under separate contract with Owner and <br />for timely incorporation of work provided and installed by Owner. Unless otherwise expressly <br />authorized in writing by the Owner’s Representative, the Contractor must integrate the <br />schedules with the Schedule of Values and unit price items so that each construction activity is <br />represented by a dollar value. <br />Float in a Progress Schedule belongs to the Owner. <br />Subcontractors shall review all schedules prior to submission to the Owner and Owner’s <br />Representative. At the Owner’s option and sole discretion, Owner may require Contractor to <br />obtain written acceptance of each schedule by Subcontractors as practical and feasible, as the <br />schedule relates to Subcontractors’ work. <br />Contractor shall not schedule any activity with an unrealistic, unduly long, or unduly short <br />duration. Contractor shall use its best efforts in good faith to set reasonable durations for all