City of Everett 01 32 11-1 June 2024 WFP Air Scour Blower Building Replacement Issued for Bid UP3813 SECTION 01 32 11 CONSTRUCTION CONSTRAINTS AND SEQUENCE PART 1 : GENERAL 1.01 SEQUENCE A. This Section describes the constraints during construction, and the guidelines for construction sequencing that the Contractor shall incorporate into the performance of the contract. 1.02 SUBMITTALS A. Construction Progress Schedule: Prepare the Contractor’s Construction Progress Schedule as defined in Section 01 32 16, based on the constraints and sequence defined herein. 1.03 COORDINATION AND SCHEDULING A. Prior to starting the work, confer with the City to develop a work schedule which will permit adjacent utilities and rights-of-way to function normally. Do not make connections between existing facilities and new work until necessary inspection and tests have been completed on the new work and it is found to conform in all respects to the requirements of the Contract Documents. B. Connection to existing services or utilities, or other work that requires temporary shutdown of any existing operations or utilities shall be planned in detail with appropriate scheduling of the work and coordinated with the City or other impacted utilities. The approved schedule for shutdown or restart shall be indicated on the Contractor’s Progress Schedule, and advance notice shall be given in order that the City may witness the shutdown, tie-in, and startup. 1.04 CONSTRUCTION SEQUENCING A. The construction sequence is provided on Drawing G 2. The construction sequence is provided for Contractor reference only and does not imply direction, means, or methods of construction. The Contractor shall be responsible for completing all elements of work as described in the Contract Documents. 1.05 LONG LEAD ITEMS A. The project will require the Contractor to procure a pre-engineered metal building, and electrical and mechanical equipment, which may be subject to long lead times. The Contractor shall notify the City/Engineer promptly of any equipment or materials with long lead times which prevent the Contractor from completing the project within the Contract Time. Any suspension of Work shall be in accordance with Section 5.3 Suspension Procedures of Specification Section 00 72 00, General Conditions. Any extension of Contract Time shall be in accordance with Section 5.2.2.2 Extensions of Contract Time of Specification Section 00 72 00, General Conditions.