Section 01 32 11 CONSTRUCTION CONSTRAINTS AND SEQUENCE City of Everett 01 32 11-2 June 2024 WFP Air Scour Blower Building Replacement Issued for Bid UP3813 1.06 WORK CONSTRAINTS A. The following is a list of work constraints by which the Contractor shall comply with during construction of the new facilities: 1. Provide temporary erosion, sedimentation, and dust control for containment of materials within the construction sites. 2. All work shall comply with applicable permits obtained for the project, including hours of operation and noise restrictions. 3. Providing vehicle and personal access to all on-site existing facilities. B. The Contractor shall schedule and conduct his/her work in a manner consistent with achieving these purposes and shall comply with the specific limitations hereinafter specified. C. Air Scour System Shutdown Limitations: 1. April 15th – September 15th (high demand season): a. 4 hours maximum downtime in a single 24-hour period. 2. September 16th – April 14th (low demand season): a. 8 hours maximum downtime in a single 24-hour period. D. Compressed Air System Shutdown Limitations: 1. Maximum 1 hour to depressurize the system, make the connection, test the system, and restore the system. PART 2 : PRODUCTS Not Used. PART 3 : EXECUTION Not Used. END OF SECTION 01 32 11