51 <br />ARTICLE 4 PHYSICAL CONDITIONS AND REFERENCE POINTS <br />4.1 Unforeseen Physical Conditions <br />Contractor shall promptly notify Project Manager in writing of any latent physical conditions at the site <br />or in an existing structure differing materially from those indicated or referred to in the Detailed Scope <br />of Work. Project Manager will promptly review those conditions. If Project Manager finds that there <br />are latent physical conditions which differ materially from those intended in the Detailed Scope of <br />Work, Project Manager will prepare a Supplementary Job Order incorporating modifications to plans <br />and specifications as necessary to proceed with and complete the Work. <br /> <br />END ARTICLE 4