December 2024 Page 6 of 9 Jacobs Engineering Group Subtask 2440P – Issue for Bid Documents - Pacific Avenue Assumptions: • See Subsection 2, “Assumptions for Amendment No. 2” in front of this document. • Same drawings as at 100%. • Only limited changes, consistent with previous comments and decisions and items noted at the 100% design workshop. • BNSF Shoring Design and Permit: o The shoring design is to facilitate the SRI connection vault construction. The estimated interior shoring dimensions are 20’ x 40’. o Three rounds of submittals:  90% to City  Permit submittal to BNSF  Final permit submittal with BNSF comments incorporated. o Specifications will be based on the City’s APWA and WSDOT format specifications. Activities: • The Consultant will visually examine the project site to verify that site conditions have not changed since the time of initial site survey and notify/discuss any significant findings which may have an impact on proposed improvements. • The Consultant will prepare construction plans and specifications by completing final design and incorporating comments from previous design submittal. • The Consultant will submit final documents for bidding. • BNSF Shoring Design and Permit: o Review existing conditions and documents. o Prepare Geotechnical and Structural Design Recommendations for Shoring Design. o Provide shoring design to meet “BNSF UTILITY ACCOMMODATION POLICY” dated February 15, 2024. o Prepare and submit permit, draft and final including incorporation of BNSF comments.  Includes coordinating with BNSF during the permitting process at the City’s direction. o Specification updates:  Modify Bid Item Description (Division B).  Modify Division 1 to add language requiring Contractor to take on schedule risk and permitting requirements related to any contractor initiated shoring changes that impact the BNSF permit.  Update special provisions related to shoring (Section 2-09 Structure Excavation).  Add Appendix for approved BNSF shoring permit. o Drawing updates:  Update C114 and C124 with additional shoring requirements.  Add two sheet for structural notes related to shoring.  Add sheet for shoring plan.  Add sheet for shoring details.