CITY OF EVERETT SPECIAL PROVISIONS <br />LS47-Beverly Lake Sewer Replacement Division 1 – GENERAL REQUIREMENTS January 30, 2025 <br />WO No – UP3529 SP – 116 <br />without any further obligation to the Contractor. Any such termination for default shall <br />not in any way operate to preclude the City from also pursuing all available remedies <br />against Contractor and its sureties for said breach or default. <br />1-08.10(10) Waiver of Remedies for Any Breach <br />(******) <br />In the event that the City elects to waive its remedies for any breach by Contractor or <br />any covenant, term or condition of this Contract, such waiver by the City shall not limit <br />the City’s remedies for any succeeding breach of that or of any other term covenant, or <br />condition of this Contract. <br />1-08.10(11) Possession and Use of Completed Portions of the Work <br />(******) <br />The City shall have the right to take possession of and use completed or partially <br />completed portions of the Work even though the time for completing the Work for such <br />portions may not have expired. Operations and maintenance costs of use of such work <br />will be borne by the City. Such possession and use shall not be deemed as acceptance <br />of the Work. If such prior possession or use increases the cost of the Work, the <br />Contractor may be entitled to request extra compensation by giving Notice and following <br />the procedures of 1-04.5 NOTICE BY THE CONTRACTOR and 1-09.11 DISPUTES <br />AND CLAIMS within five calendar days of each occurrence. The Contractor shall not <br />submit a Contract Claim for possession by the City of portions of the Work specifically <br />required in the Contract Documents to be placed into use or operation or both before <br />completion of the entirety of the Work. <br />1-08.10(12) Possession of Incomplete Portions of the Project <br />(******) <br />Should the Contractor fail to meet any date specified for Substantial Completion or <br />Physical Completion of Work or any portion of Work requiring early possession and use <br />by the City, the City may, after a 14 calendar day Notice to the Contractor, take over such <br />portion or any Work that is behind schedule. In such case, the City’s Representative will <br />prepare a list of incomplete Work taken over by the City. The cost of City's work will be <br />charged to and deducted from amounts due to the Contractor. The Substantial <br />Completion date of the entire or a portion of the Project will be established as the date <br />when the City actually begins using the Project or portion of the Project for its intended <br />purpose. Division of responsibilities between City and Contractor, beginning of <br />warranties, and any other issues relating to Substantial Completion shall be as specified <br />in 1-08.5(2) SUBSTANTIAL COMPLETION. <br />Supplement Section 1-08 by adding the following: <br />1-08.11 Record Drawings <br />(******) <br />1-08.11(1) Description <br />This section specifies the requirements for preparing record drawings. The Contractor, <br />with the cooperation and assistance of the City Inspector, is responsible for marking up <br />record drawings during the course of construction and documented in Autodesk BUILD <br />using the “markup” tool. The Contractor shall keep the record drawings up to date at all <br />times during the course of construction. <br />The Inspector will verify the record drawings are accurate and complete before accepting <br />the Contractors monthly pay request. If the record drawings are not current or accurate, <br />the pay request will not be processed. <br />As the Contract approaches Final Acceptance, prepare, with the assistance of the <br />Inspector, a complete and accurate set of record drawings. The Inspector must approve