CITY OF EVERETT SPECIAL PROVISIONS
<br />
<br />LS 47 – Beverly Lake Sewer ReplacementDivision B – BID DESCRIPTIONS January 30, 2025
<br />WO No. – UP3529 SP - 15
<br />
<br />The unit contract price for PVC SIDE SEWER LATERAL, 6-Inch Diam., shall constitute full
<br />compensation for all labor, materials, tools and equipment necessary to furnish and install
<br />the pipe, restrained joints (where shown on the Plans or as required by the Standard
<br />Specifications and Special Provisions), and all fittings, including tees, crosses, reducers,
<br />couplings, material transitions and sleeves required for complete installation along the run of
<br />each pipe size, as shown on the Plans and specified herein, and additionally, shall include,
<br />but not be limited to, the following:
<br />(i) Removal of structures or obstructions not specifically covered under other Bid
<br />Items. This shall include, but not be limited to, removal and disposal of the
<br />existing asphalt or concrete pavement, sidewalk, curb, thrust blocks,
<br />miscellaneous landscaping, and sod as indicated on the Plans.
<br />(j) All required potholing to verify locations of water service crossings and existing
<br />utilities. The costs for potholing and excavation required to determine exact
<br />depths and locations of other utilities shall be included with this Work with no
<br />direct compensation made.
<br />(k) Utility or light pole holding in conformance with the requirements of the applicable
<br />utility including, if necessary, arranging for the utility to hold poles and paying the
<br />associated fees.
<br />(l) Where trench excavation is proposed, dewatering, installation of pipe, furnishing,
<br />placing, and compacting sand backfill for pipe bedding, furnishing, placing and
<br />compacting suitable native material for trench backfill and placing and
<br />compacting imported backfill material. No extra payment shall be made for
<br />removing, loading, hauling, and disposing of displaced and unsuitable material.
<br />(m) Maintenance, restoration and/or relocation, if required, of existing culverts, storm
<br />drainage pipe, other utilities and structures affected by construction that are to
<br />remain.
<br />(n) Ethafoam pads or sand backfill between sewer and other pipes.
<br />(o) Maintenance of existing sewer and provisions for interim service.
<br />(p) Extra depth, including excavation, backfill and compaction required to clear
<br />known buried utilities or other known obstacles.
<br />
<br />Bid Item 29 - Manhole, Type 3, 48-inch DIA.
<br />Measurement and Payment: Unit Price per Each (EA)
<br />The unit price per each manhole shall be full compensation for all labor, material, tools and
<br />equipment necessary to satisfactorily complete the work as defined in these Contract
<br />Documents.
<br />The unit price per each manhole shall be full compensation for furnishing, hauling, and
<br />assembling in place the completed installation including all manholes, frames and covers,
<br />pipe connections, special fittings, joint materials and penetrations.
<br />The unit price of per each manhole shall also include, but not be limited to, all costs for
<br />excavation; hauling and disposing of surplus or unsuitable material; dewatering; sewer flow
<br />bypassing; furnishing and installing couplings; furnishing and installing steps or ladder;
<br />placing and compacting native backfill; furnishing, placing, and compacting foundation
<br />material as required; cleaning and flushing manholes; reconnecting existing sanitary sewer
<br />connections; and replacing, protecting and maintaining utilities.
<br />All costs associated with abandoning and/or removing and disposing of existing manholes
<br />as shown on the plans shall be included in the unit price for this bid item.
|