Stormwater Pollution Prevention Plan <br /> 4.0 Construction Phasing and BMP <br /> Implementation <br /> The BMP implementation schedule is driven by the construction schedule. The following <br /> provides a sequential list of the proposed construction schedule milestones and the corresponding <br /> BMP implementation schedule which the contractor will insert when available for the project. <br /> The list contains key milestones such as wet season construction. <br /> BMP implementation schedule listed below is keyed to proposed phases of the construction <br /> project, and reflects differences in BMP installations and inspections that relate to wet season <br /> construction. The project site is located west of the Cascade Mountain Crest. As such,the dry <br /> season is considered to be from May 1 to September 30 and the wet season is from October 1 to <br /> April 30. <br /> ■ Estimate of Construction start date: TBD <br /> ■ Estimate of Construction finish date: TBD <br /> ■ Mobilize equipment offsite: TBD <br /> ■ Mobilize and store all ESC and soil stabilization products <br /> (store materials on hand BMP C 150): TBD <br /> ■ Install ESC measures: TBD <br /> ■ Construct proposed improvements TBD <br /> ■ Wet Season starts: October, 2022 <br /> SNBL USA, LTD—Seaway Commercial Center <br /> SWPPP 11 August, 2022 <br />