Laserfiche WebLink
25 <br />Progressive Design Build General Conditions <br /> <br />8.2 Delays to the Work. <br />8.2.1 If Design-Builder is delayed in the performance of the Work due to acts, omissions, <br />conditions, events, or circumstances beyond its control and due to no fault of its own or those for <br />whom Design-Builder is responsible, the Contract Time(s) for performance shall be reasonably <br />extended by Change Order. Delays attributable to and within the control of a Subcontractor or <br />supplier shall be deemed to be delays within the control of Design-Builder. By way of example, <br />events that may entitle Design-Builder to an extension of the Contract Time(s) include acts or <br />omissions of Owner or anyone under Owner’s control (including separate contractors), changes <br />in the Work, Differing Site Conditions, Hazardous Conditions, and Force Majeure Events. <br />Design-Builder shall make all reasonable efforts to prevent and mitigate the effects of any delay, <br />whether occasioned by an act of Force Majeure or otherwise. <br />8.2.2 Design-Builder is not entitled to a change in Contract Time unless the progress of the <br />Work on the critical path is delayed and completion of the Work within Contract Time is delayed. <br />A Request for a Change Order that includes a request for an adjustment in the Contract Time <br />shall be delivered to Owner in accordance with Article 9 herein and, in addition to any <br />requirements in Article 9, shall: <br />a. Include a clear explanation of how the event or conditions specifically impacted <br />the critical path and overall construction schedule and the amount of the <br />adjustment in Contract Time requested. <br />b. Demonstrate that the delay could not have been avoided by re-sequencing of the <br />Work or other reasonable alternatives. <br />c. Be limited to the change in the critical path of a construction schedule, and any <br />updates, attributable to the event or conditions which caused the request for <br />adjustment. <br />8.3 In addition to Design-Builder’s right to a time extension for those events set forth in <br />Section 8.2.1 above, Design-Builder may also be entitled to an appropriate adjustment of the <br />GMP; except that the GMP shall not be adjusted for Force Majeure Events. <br /> <br />Article 9 <br />Changes to the GMP and Contract Time <br />9.1 Authorized Changes in the Work <br />9.1.1 General. After execution of the Contract, Changes in the Work are effective solely by <br />Change Order or Work Change Directive. <br />9.1.2 Change Order. A Change Order is a written instrument issued after execution of the <br />Contract signed by Owner and Design-Builder, stating their agreement upon all of the following: <br />9.1.2.1 The scope of the change in the Work; <br />9.1.2.2 The amount of the adjustment to the GMP, if any; and <br />9.1.2.3 The extent of the adjustment to the Contract Time(s), if any. <br />A Change Order shall constitute full payment and final settlement of all Claims for Contract Time <br />adjustment and for direct, indirect, and consequential costs, including costs of delays,