2025 FEDERAL OVERLAY, BROADWAY – CALIFORNIA ST TO 18TH ST SPECIAL PROVISIONS <br />FEDERAL AID# STBGUL-2715(012); COE PW# 3841 SP-59 May 6, 2025 <br /> <br /> 1 <br />1-09.2(5).RTF 2 <br />1-09.2(5) Measurement 3 <br />(December 30, 2022 APWA GSP) 4 <br /> 5 <br />Revise the first paragraph to read: 6 <br /> 7 <br />Scale Verification Checks – At the Engineer’s discretion, the Engineer may perform 8 <br />verification checks on the accuracy of each batch, hopper, or platform scale used in 9 <br />weighing contract items of Work. 10 <br /> 11 <br />1-09.6.RTF 12 <br />1-09.6 Force Account 13 <br />(December 30, 2022 APWA GSP) 14 <br /> 15 <br />Supplement this section with the following: 16 <br /> 17 <br />The Contracting Agency has estimated and included in the Proposal, dollar amounts for 18 <br />all items to be paid per force account, only to provide a common proposal for Bidders. All 19 <br />such dollar amounts are to become a part of Contractor's total bid. However, the 20 <br />Contracting Agency does not warrant expressly or by implication, that the actual amount 21 <br />of work will correspond with those estimates. Payment will be made on the basis of the 22 <br />amount of work actually authorized by the Engineer. 23 <br /> 24 <br />1-09.9.GR1 25 <br />Payments 26 <br /> 27 <br />1-09.9.OptionA.RTF 28 <br />1-09.9 Payments 29 <br />(July 8, 2024 APWA GSP, Option A) 30 <br /> 31 <br />Supplement this section with the following: 32 <br /> 33 <br />Lump sum item breakdowns are not required when the bid price for the lump sum item is 34 <br />less than $20,000. 35 <br /> 36 <br />1-09.9.OptionB.RTF 37 <br />1-09.9 Payments 38 <br />(July 8, 2024, APWA GSP, Option B) 39 <br /> 40 <br />Delete the fourth paragraph and replace it with the following: 41 <br /> 42 <br />Progress payments for completed work and material on hand will be based upon 43 <br />progress estimates prepared by the Engineer. A progress estimate cutoff date will be 44 <br />established at the preconstruction conference. 45 <br /> 46 <br />The initial progress estimate will be made not later than 30 days after the Contractor 47 <br />commences the work, and successive progress estimates will be made every month 48 <br />thereafter until the Completion Date. Progress estimates made during progress of the 49 <br />work are tentative, and made only for the purpose of determining progress payment. 50