I <br /> I Drainage Report <br /> Boeing Everett-E-6 Parking Lot Expansion July 16, 2013 <br /> I are deeper and will run under the expanded parking lot to the west and north. Access to the <br /> existing site is from a two-way driveway near the SW corner of the existing parking lot. TABLE <br /> 1 summarizes the existing site conditions and land cover. The drainage basin is the project limits <br /> I as no offsite flow enters the site's drainage system from either offsite or from the existing asphalt <br /> parking lot. <br /> I 1.2 Developed Site Conditions <br /> The developed site conditions, shown in the project plans submitted under separate cover, will <br /> include an additional 51,141 SF of asphalt surrounding the existing asphalt parking lot on three <br /> I sides. The north expansion area consists of 16,888 SF, the west expansion consists of 18,886 SF, <br /> and the south expansion adds 15,367 SF of new asphalt pavement. Drainage for the developed <br /> site will be collected by new Type 1 and Type 2 catch basins connected to the existing drainage <br /> I system serving the existing parking lot. New pavement surfaces will be graded to prevent surface <br /> flows into the existing parking lot and the proposed catch basins will include downturned 90- <br /> degree elbows for spill control and oil/water separation. A landscape strip will remain along the <br /> I west side of the proposed parking lot separating the lot from the one-way road to the west. <br /> TABLE 1 summarizes the developed site conditions and land cover. <br /> 1.3 Site Area and Size of Improvements <br /> I <br /> The project site is a 2.6 acre area located in the southeast corner of Boeing Everett's north <br /> campus, adjacent to Highway 526 and Seaway Blvd. The drainage basin for the project <br /> I improvements is the improved area itself as no offsite flow enters the site from any direction. <br /> There is an existing electrical substation to the north of the existing site, with electrical <br /> transmission lines running overhead near the east edge of the existing site. The site area and size <br /> of improvements are shown in the project plans and summarized in TABLE 1. See APPENDIX <br /> ID for the Site Plan of the project. <br /> I <br /> I <br /> I <br /> I <br /> I <br /> I <br /> 20130715_Drainage Report_Boeing Everett_Gate E-6 Parking Lot.doc Page 2 <br />