Stormwater Pollution Prevention Plan <br /> 4.0 Construction Phasing and BMP <br /> Implementation <br /> The BMP implementation schedule will be driven by the construction schedule. The following <br /> provides a sequential list of the proposed construction schedule milestones and the corresponding <br /> BMP implementation schedule. The list contains key milestones such as wet season <br /> construction. <br /> The BMP implementation schedule listed below is keyed to proposed phases of the construction <br /> project, and reflects differences in BMP installations and inspections that relate to wet season <br /> construction. The project site is located west of the Cascade Mountain Crest. As such, the dry <br /> season is considered to be from May 1 to September 30 and the wet season is considered to be . <br /> from October 1 to April 30. <br /> The BMP implementation schedule is driven by the construction schedule. The following <br /> provides a sequential list of the proposed construction schedule milestones and the corresponding <br /> BMP implementation schedule. The list contains key milestones such as wet season <br /> construction. <br /> BMP implementation schedule listed below is keyed to proposed phases of the construction <br /> project, and reflects differences in BMP installations and inspections that relate to wet season <br /> construction. The project site is located west of the Cascade Mountain Crest. As such,the dry <br /> season is considered to be from May 1 to September 30 and the wet season is considered to be <br /> from October 1 to April 30. <br /> • Estimate of Construction start date: 09/ 01/2013 <br /> • Estimate of Construction finish date: 09 /30/2014 <br /> • Mobilize equipment on site: 09/05 /2013 <br /> • <br /> • Mobilize and store all ESC and soil stabilization products <br /> (store materials on hand BMP C150): 09 / 10 /2013 <br /> • Install ESC measures: 09/ 10/2013 <br /> • Install stabilized construction entrance: 09 / 15 /2013 <br /> ■ Begin clearing and grubbing: 09 /20/2013 <br /> ■ Demolish existing pavement: 09/21 /2013 <br /> • Excavation for building foundations 09 /30/2013 <br /> 15 <br />