Laserfiche WebLink
City of Everett 00 73 73 - 4 <br />Port Gardner Storage Facility - Facility Construction Package WO# UP-3525 <br />00 73 73 - 4 APPRENTICE UTILIZATION <br />When the Contractor fails to meet the Apprenticeship goal of 15%, a penalty will be assessed <br />for each hour that is not achieved, unless a Good Faith Effort is approved by the Owner. <br />Apprenticeship Utilization Penalty will be calculated as described below: <br />Percent of goal met Penalty per hour of unmet goal <br />100%$0.00 <br />90% to 99%$2.00 <br />75% to 89%$3.50 <br />50% to 74%$5.00 <br />1% to 49%$7.50 <br />0%$10.00 <br />The Contractor shall include all related costs in the Bid prices of the Contract, including but <br />not limited to implementing, developing, documenting, and administering an apprenticeship <br />utilization program, recording and reporting hours and all other costs to comply with this <br />provision. <br />Other capitalized terms are as defined elsewhere in the Contract Documents. <br />END OF SECTION