City of Everett 01 12 16 - 8 <br />Port Gardner Storage Facility - Facility Construction Package WO# UP-3525 <br /> <br /> <br />01 12 16 - 8 WORK SEQUENCE <br />14. West Marine View Drive Conveyance Project (WMVD): <br />a. This Storage Facility Construction Package includes installation of capped <br />pipelines that terminate near the project boundary along Lower Norton Avenue <br />on the eastern boundary of the project site. The ends of these pipes will <br />connect with newly installed conveyance lines constructed under a separate <br />concurrent contract - the West Marine View Drive Conveyance project, <br />Construction Package 2 (WMVD). The Contractor shall coordinate with the <br />Owner and WMVD contractor to avoid potential conflicts with construction <br />along Lower Norton Avenue, share use of staging areas outside of the PGSF <br />property boundaries and as needed within PGSF property boundaries for <br />making said pipeline connections by WMVD Construction Package 2, and <br />ensure access to both the PGSF and WMVD project sites. <br />b. Schedule: <br />1) Drawing C-10-1303: <br />a) As identified on the drawing, Contractor shall complete and provide <br />access to the pipe connection points under Keynote #17 for the <br />WMVD Construction Package 2 project contractor no later than <br />August 1st, 2026. Following installation of the connection points <br />included in the PGSF Contract, the PGSF Contractor shall pause <br />work in this area to accommodate construction of the WMVD <br />Construction Package 2 pipelines that will join to these connection <br />points. <br />The WMVD Package 2 contractor will complete the pipe connections, <br />backfill the connection points and WMVD piping and improve the area <br />to provide a drivable surface on Lower Norton Ave east of the <br />property lines indicated on Drawing C-10-1303 and as generally <br />indicated in Specification 01 12 16 Exhibit A-4.2, tiles C-2109, C-2209 <br />and C-2309 no later than December 31, 2026. Final site restoration <br />within the scope of WMVD Package 2, including curbing, pavement, <br />and other finish work is anticipated to be completed towards the end <br />of the WMVD project in the 3rd and 4th quarters of 2027. <br />From August 1st, 2026 – December 31, 2026 assume access to the <br />PGSF site from the Marine View Drive southbound offramp and to <br />northeast of the PGSF site through access gates noted on Drawing C- <br />00-0002, Keynote #8. <br />Following completion of the WMVD Contract 2 work, complete the <br />outstanding work along the eastern project boundary that was paused <br />to accommodate WMVD Construction Package 2. This outstanding <br />work may include items such as permanent power, shallow utilities, <br />pavement, lighting, and fencing. <br />The exact extent of the pause work area and the necessary <br />sequencing during this pause work period shall be coordinated with <br />the Owner and Owner’s Representative and reflected in the baseline <br />Progress Schedule with refinement with Progress Schedule updates <br />as coordination continues between the Owner and concurrent WMVD <br />contracts and WMVD Contract 2 schedule is developed and made <br />known. <br />