Laserfiche WebLink
City of Everett 01 12 16 - 9 <br />Port Gardner Storage Facility - Facility Construction Package WO# UP-3525 <br /> <br /> <br />01 12 16 - 9 WORK SEQUENCE <br />b) Underground utilities south of Area 30: <br />Contractor shall complete installation of 16” CS, 42” CS, CSMH 15- <br />01, and CSMH-15-02 no later than August 1st, 2026 and make the <br />corridor passable for construction access. The area between the Port <br />of Everett property and Area 30 shall be used as an access point to <br />the PGSF to complete work noted under Paragraph 1.7 B. 13. b. 2) <br />when access from the north is impeded by potential closure the <br />Marine View Drive southbound offramp and WMVD Contract 2 <br />construction prevents access through parking lot gates North of Area <br />70. <br />2) Drawing C-10-1304: <br />a) As identified on the drawing, Contractor shall complete and provide <br />access to the pipe connection points under Keynote #11 for the <br />WMVD project Contractor no later than August 1st, 2026. Following <br />installation of the connection points included in the PGSF Contract, <br />the PGSF Contractor shall pause work in this area to accommodate <br />construction of the WMVD Construction Package 2 pipelines that will <br />join to these connection points. <br />The WMVD Contract 2 contractor will complete the pipe connections, <br />and backfill the connection points and WMVD piping and improve the <br />area to provide a drivable surface on Lower Norton Avenue east of <br />the property lines indicated on the Drawing C-10-1304 and as <br />generally shown in Specification 01 12 16 Exhibit A-4.3, tiles C-2110, <br />C-2111, Exhibit A-4.4 tiles C-2210, C-2211 and Exhibit A-4.5 tiles C- <br />2310, C-2311 from January 1st, 2027 through May 31st, 2027. Final <br />site restoration within the scope of WMVD Package 2, including <br />curbing, pavement, and other finish work is anticipated to be <br />completed towards the end of the WMVD project in the 3rd and 4th <br />quarters of 2027.From January 1, 2027 – May 31, 2027assume <br />access to the PGSF site from the southeast corner of the PGSF site, <br />between the Port of Everett Terminal and Area 30. <br />Following completion of the WMVD Contract 2 work, complete the <br />outstanding work along the eastern project boundary that was paused <br />to accommodate WMVD Construction Package 2. This outstanding <br />work may include items such as shallow utilities, pavement, lighting, <br />and fencing. <br />The exact extent of the pause work area and the necessary <br />sequencing during this pause work period shall be coordinated with <br />the Owner and Owner’s Representative and reflected in the baseline <br />Progress Schedule with refinement with Progress Schedule updates <br />as coordination continues between the Owner and concurrent WMVD <br />contracts and WMVD Contract 2 schedule is developed and made <br />known. <br />c. Access: