City of Everett 00 72 00 - 46 00 72 00 - 46 GENERAL CONDITIONS 12.4.2 Extra Work 12.4.2.1 Adjustment of Contract Sum If the Contractor is entitled to an adjustment of Contract Sum because of Extra Work, the adjustment shall be calculated and paid as provided in 9.5. ADJUSTMENT OF CONTRACT SUM. This amount includes jobsite and home office Overheads for such Work, including any schedule delays relating to such Work. Therefore, no compensation in addition to that provided in 9.6. FORCE ACCOUNT shall be paid for such things as extended Overhead or other costs or damages. 12.4.2.2 Extension of Contract Time Extensions of Contract Time caused by Extra Work shall be determined as provided in 5.2.2.2 Extensions of Contract Time. 12.4.3 Delays 12.4.3. Owner Caused Delay Unrelated to Extra Work 12.4.3.1.1 Adjustment of Contract Sum If the Contractor is entitled to an adjustment of Contract Sum because of a Delay solely caused by the Owner that does not relate to Extra Work, Contractor shall only be compensated for the items below, less all funds paid pursuant to any change in the Contract Sum that contributed to the Delay: 1. Documented, incurred cost of nonproductive field supervision or labor extended because of the Delay; 2. Documented, incurred cost of home office supervision to attend jobsite meetings; 3. Documented, incurred cost of temporary facilities or equipment rental extended because of the Delay; 4. Documented, incurred cost of insurance extended because of the Delay; 5. General and administrative Overhead in an amount to be agreed upon, but not to exceed three percent (3%) of original Contract Sum divided by the Contract Time for each day of the Delay. Owner shall not owe Contractor compensation for extended Overhead or other delay costs to the extent Contractor or anyone other than the City contributed to or is concurrently responsible for the Delay. 12.4.3.1.2 Adjustment of Contract Time If the Contractor is entitled to an adjustment of Contract Time because of a Delay solely caused by the Owner that does not relate to Extra Work, Contractor shall be entitled to an adjustment of Contract Time to the extent the Delay increases the duration of the Project, as measured by the critical path and as demonstrated pursuant to the requirements of 5.2.2.2 Extensions of Contract Time. 12.4.3.2 Contractor Caused Delay If the Contractor is solely responsible for any Delay to any interim milestone, Substantial Completion, Physical Completion or the Completion Date, the Owner shall be entitled to liquidated or other damages as provided elsewhere in the Contract Documents. The Contractor accepts the risk of any Delays caused by strikes, work slowdowns, job actions and labor unrest of any kind. Contractor shall not be entitled to any increase in Contract Sum or Contract Time due to a Delay it caused. 12.4.3.3 Delays Concurrently Caused by Contractor and Owner If the Owner and the Contractor cause a Delay concurrently, neither the Owner nor the Contractor shall be liable to the other except as provided herein. 12.4.3.3.1 Adjustment of Contract Sum The Contractor shall not be entitled to any adjustment in Contract Sum for Delays concurrently caused by the Owner and the Contractor.