CITY OF EVERETT SPECIAL PROVISIONS <br />Greely St. Water Quality Retrofit Division 1 – GENERAL REQUIREMENTS January 2026 <br />WO No. UP3817 SP – 63 <br />5. An analysis of the progress schedule showing the impact to the schedule <br />resulting from the change or disruption, if the Contractor is asserting a <br />schedule change or disruption; <br />Throughout any work related to a Notice, the Contractor shall keep complete and <br />accurate records of costs, expenses, and time incurred for which Contractor will or may <br />seek an adjustment. Contractor waives and is estopped from seeking an adjustment of <br />Contract Sum or Contract Time where Contractor fails to keep and maintain cost, <br />timekeeping, and scheduling records segregated and contemporaneously allocated to <br />the subject work for which an adjustment is sought. For example, failure to keep <br />contemporaneous labor and equipment time records specifically and only allocated to <br />each item of claimed Extra Work shall constitute a waiver of any Contract Claim for <br />reimbursement or additional Contract Time for each such item of Extra Work. The <br />Contractor shall permit the City access to these and any other records needed for <br />evaluating requests for additional Contract Time or Contract Sum. <br />1-04.5(4) Contract Claim <br />A Contractor dissatisfied with the City’s response or (non-response) to a Notice provided <br />under Section 1-04.5 completely waives any claims related to such Notice unless the <br />Contractor submits a Contract Claim in accordance with Section 1-09.11. <br />1-04.7 Differing Site Conditions (Changed Conditions) <br />Delete all of 1-04.7 and substitute the following: <br />Upon discovery and before such conditions are disturbed, the Contractor shall promptly <br />provide Notice to the City’s Representative of: <br />Pre-existing subsurface or latent physical conditions at the site differing materially <br />from those indicated in this Contract, or <br />Pre-existing unknown physical conditions at the site, of an unusual nature, differing <br />materially from those ordinarily encountered and generally recognized as inhering <br />in work of the character provided for in this Contract. <br />Upon written request, the City’s Representative shall determine whether the actual <br />conditions encountered by the Contractor conditions are materially different and, if so, <br />are the cause of a material increase or decrease in the Contractor’s cost of performance <br />of the Work, or extend the duration of the critical path of the schedule. Upon such <br />determination, the City's Representative will make an adjustment of Contract Sum or <br />Contract Time, as appropriate. Extensions of Contract Time will be evaluated in <br />accordance with 1-08.3 PROGRESS SCHEDULE. <br />The City's Representative’s determination that differing site conditions do not exist <br />and/or the appropriate adjustment in Contract Sum or Contract Time (if any) shall be <br />final. If there is a decrease in the cost or time required to perform the Work, failure of <br />the Contractor to notify the City’s Representative of the differing site condition shall not <br />affect the City’s right to make an adjustment in the Contract Sum or Contract Time. <br />Additionally, no Contract Claim or adjustment of Contract Sum or Contract Time shall be <br />allowed unless the Contractor has followed the procedures provided for in this Contract, <br />including, but not limited to, furnishing timely Notice of the event and its effect on <br />Contract Time and Contract Sum as required herein. <br />Contractor shall in no event be entitled to a Contract Claim or adjustment of Contract <br />Sum or Contract Time based on an allegation that the pre-existing subsurface or latent <br />physical conditions at the site differ materially from those indicated in this Contract <br />unless Contractor establishes that it reasonably relied on the conditions indicated in this <br />Contract when making its bid, that the actual conditions encountered on the site differed