Laserfiche WebLink
Port Gardner Storage Facility West Marine View Drive Storm and Combined Sewer - Exhibit A Scope of Work <br />33 <br />Task 1054.4 Geotechnical Construction Services <br />Activities/Approach: <br />Geotechnical construction services are being led by HWA GeoSciences Inc. (HWA) and include the <br />following: <br />•Participate in project kickoff meeting (2 staff at 4 hours each) and up to five (5) construction <br />coordination meetings (2 staff at 1 hour each). <br />•Provide consultation for geotechnical aspects of the project that arise during construction. <br />•Up to 480 hours (15 hours per structure for 32 structures) to provide periodic site visits to <br />verify that subgrade soils are suitable to provide support for the proposed structures. If <br />needed, additional subgrade inspections will be conducted under the Construction <br />Management (CM) contract. Material and compaction testing will be completed under the <br />third-party CM contract. <br />•As needed, provide part-time or full-time observation of the excavation and construction of <br />the temporary shoring. This will include observation of sheet pile driving, soldier pile and <br />monitoring for caving, verification that adequate depth is achieved, and placement of <br />concrete and backfill. Up to five (5) part-time visits at 6 hours per day and five (5) full-time <br />visits at 10 hours per day. Additional time may be required depending on Contractor’s <br />progress, budget will be added by amendment or reallocated from other tasks as mutually <br />agreed. <br />•Micropile Load Test Observation: HWA will provide full-time observation of micropile load test <br />per Project Specifications for Package 2. We anticipate this task will take about 3 workdays <br />of 12 hours per day including time for coordination, travel, and preparation of daily field <br />reports. <br />•Full-Time Observation of Micropile Installation: HWA will provide full-time observation of <br />micropile installation completed for Package 2. This will include observation of installation <br />methods, soil cuttings, and verification that adequate depth is achieved. We anticipate this <br />task will take about 16 workdays of 12 hours per day including time for coordination, travel, <br />and preparation of daily field reports. <br />•Prepare a summary field inspection report for submittal to the City, documenting the <br />observed construction activities. <br />•Provide on-call response with environmental sampling for unanticipated contaminated <br />conditions that may arise during construction. Each on-call response is estimated to require <br />approximately 12 hours for coordination with the analytical laboratory; travel; time on-site; <br />sample submittal to the laboratory; analytical data review and tabulation; and preparation of <br />field reports. All environmental samples will be submitted to the laboratory on a rush (1 to 2 <br />day) turnaround time. Resulting environmental field reports will be provided the day after <br />final laboratory results are received. This task includes up to 5 on-call responses. <br />•Provide the City and/or Contractor with waste profiling assistance by preparing applicable <br />portions of waste profile documents for proper disposal of contaminated materials. The City <br />or Contractor will sign as the “generator” of all waste profile documents. <br />•BC will attend up to six (6) site visits (10 hours each including preparation and travel) for <br />geotechnical observations and coordination. <br />Assumptions: