City of Everett 00 7200 - 18 <br />2026 WPCF Biosolids Removal & Disposal UT 3752-30 <br /> <br /> <br /> <br />00 7200 - 18 GENERAL CONDITIONS <br />along the affected paths of the reviewed Preliminary Schedule at the time the change was authorized in <br />writing by the Owner. Contractor has the burden of clearly and convincingly demonstrating entitlement <br />to any adjustment of Contract Time. <br />If the Owner is solely responsible for any Delay to Substantial Completion, Physical Completion, <br />Completion Date, or Final Acceptance, the Contractor shall only be entitled to compensation or other <br />damages as described in 12.4 REMEDIES, provided that Contractor timely gave Notice pursuant to <br />ARTICLE 10. NOTICE TO OWNER, timely submitted a Contract Claim pursuant to ARTICLE 12. <br />CONTRACT CLAIMS and fulfilled the requirements of 5.2.2. Construction Schedule. <br />5.2.3. Construction Progress <br />The Contractor shall furnish all labor, materials, facilities and Equipment necessary to insure the <br />prosecution and completion of the Project within the interim milestones, Substantial Completion, Physical <br />Completion and Completion Dates of the Contract. If Work falls seven (7) days or more behind the <br />reviewed Preliminary Schedule, the Contractor agrees that, at its sole cost and expense, it will take all <br />actions necessary to return the Project to the accepted schedule. These actions may include the following: <br />1. Increase labor in quantities and crafts. <br />2. Increase the number of working hours per shift, shifts per working day, working days per week, <br />or the amount of Equipment, or any combination of the foregoing. <br />3. Reschedule activities. <br />If requested by the Owner’s Representative, the Contractor shall prepare a proposed schedule revision <br />demonstrating a plan to make up the lag in progress and insure completion of the Work within the <br />Contract Time. All actions taken to return the Project to the accepted schedule are at the Contractor's <br />expense. <br />The Contractor shall pay all costs incurred by the Owner that result from the Contractor's action to return <br />the Project to its accepted schedule, including, but not limited to, additional, overtime, or third party <br />inspection, design and construction management service costs. Contractor agrees that Owner shall deduct <br />such charges from payments due the Contractor. It is further understood and agreed that none of the <br />services performed by the Owner’s Representative in monitoring, reviewing and reporting Project status <br />and progress shall relieve the Contractor of responsibility for planning and managing construction Work <br />in conformance with the construction schedule. <br />5.2.4. Delays <br />5.2.4.1 General <br />In the event of a Delay, the Contractor shall take immediate steps to minimize the Delay or avoid further <br />Delay. The Contractor agrees it shall not make any Contract Claim or request for adjustment of Contract <br />Time or Contract Sum based upon Delays for which it did not timely provide Notice to the Owner. <br />5.2.4.2 Bonuses <br />If the Contract Documents provide the Contractor with a bonus or other incentive for early completion of <br />a milestone or other completion point, Contractor assumes the risk of Delays caused wholly or partially <br />by third parties. Owner shall not pay any bonus that Contractor would have achieved but for any and all <br />Delays caused in whole or in part by a third party. By way of example only, the Contractor bears the risk <br />of utility companies’ failure to locate underground utilities accurately and the Contractor bears the risk of <br />timely asking for the marking of the location of underground utilities. <br />5.3. SUSPENSION PROCEDURES <br />The Owner may, at its convenience and at any time and without cause, suspend all or any part of the <br />Work by notice in writing to the Contractor. The Work shall be resumed by the Contractor within five (5) <br />days after receiving written notice from the Owner to do so. The Contractor will be allowed an increase