City of Everett 00 7200 - 19 <br />2026 WPCF Biosolids Removal & Disposal UT 3752-30 <br />00 7200 - 19 GENERAL CONDITIONS <br />in the Contract Sum or an extension of Contract Time, or both, directly attributable to any suspension in <br />accordance with the Change Order procedures herein; provided, (1) the Contractor shall not be entitled to <br />any increase to the extent caused by the Contractor and (2) Contract Sum increases and Contract Time <br />extensions for suspension caused by Third Parties or Force Majeure Events are limited as set forth in <br />12.4.3.4 Third Party Caused Delays and Force Majeure. <br />5.4. TERMINATION PROCEDURES <br />5.4.1. Termination by Owner for Default <br />The Owner may terminate the Contract upon written notice to Contractor and its surety whenever the <br />Contractor is deemed to be in default or fails to fulfill, in a timely and proper manner, one or more <br />Contract obligations, or is in violation of any provisions or covenants of the Contract. Termination shall <br />be effective upon receipt of such notice by the Contractor. <br />For purposes of this paragraph, the Contractor shall be deemed to be in default upon the occurrence of <br />any one or more of the following events: <br />1. If Contractor is bankrupt or insolvent. <br />2.If Contractor makes a general assignment for the benefit of creditors. <br />3. If a trustee or receiver is appointed for Contractor, or for any of Contractor's property. <br />4. If Contractor files a petition to take advantage of any debtor's law, or to reorganize under any <br />bankruptcy chapter or law. <br />5. If Contractor repeatedly fails to make prompt payments to Subcontractors or others for labor, <br />materials, or Equipment. <br />6. If Contractor disregards laws, ordinances, rules, regulations, or orders of any public body having <br />jurisdiction. <br />7. If Contractor disregards the authority of the Owner or Owner’s Representative. <br />8. If Contractor violates in a substantial way the provisions of the Contract Documents or fails, <br />neglects, or refuses to proceed in compliance with the provisions of the Contract Documents. <br />9.If the Contractor made material misrepresentations to the Owner with respect to: (a) its <br />qualifications or those of its Subcontractors; (b) its or its subcontractors’ ability to perform the <br />Work in a timely, workmanlike manner; (c) the materials installed or to be installed; or (d) <br />progress pay estimates. <br />10.If Contractor fails to supply sufficient skilled workers or suitable materials or equipment. <br />11.If Contractor refuses or fails to prosecute the Work with such diligence as will ensure its Physical <br />Completion within the original Physical Completion time and any extensions of time which may <br />have been granted to the Contractor by change order or otherwise. <br />12. If Contractor performs Work which deviates from the Contract. <br />13. If Contractor otherwise violates in any material way any provisions or requirements of the <br />Contract. <br />After termination of the Contractor for default, the Owner may transfer performance of the Work to the <br />Contractor's surety. The Owner may exclude the Contractor from the Site and take possession of the <br />Work and all of the Contractor's tools, appliances, owned or rented construction equipment, and <br />machinery at the Site and use the same to the full extent they could be used by the Contractor. The <br />Owner may incorporate in the Work all materials and Equipment stored at the Site or for which the <br />Owner has paid the Contractor, but which are not yet on Site. In such case, the Contractor will not be