Project: Shore Avenue Storm Water Outfall Improvements Project <br /> Change Order No.2 <br /> Change Order Effective Date: May 11, 2016 <br /> New Item #203—Asphalt Extruded Curb. This item pays for the new asphalt curb installed along <br /> Shore Avenue, as a result of the street reconstruction approach taken, given the excessive sloughing of <br /> existing soils during trench excavation. <br /> New Item #204—Cost for Second Changed Conditions Notice. Between Sound Avenue and 33rd <br /> Avenue West along Shore Avenue,the new storm trench followed alongside an existing 8-inch <br /> perforated French drainage trench system. This perforated French drain trench system was lined with <br /> plastic and backfilled with drain rock to a depth of 4-5 feet and at various locations, generally ran <br /> parallel to and either along the south side or north side of the new storm sewer trench pipe being <br /> installed by Thomco. The material would sloughed into contractors storm sewer trench line, at times <br /> requiring it to be removed and at other times just slowing the dragging of the trench box forward, in <br /> order to control the sloughing and loss of added roadway width during the pipe backfilling process. <br /> This cost is to reimburse the contractor for the added labor and equipment and dump fee costs caused <br /> by the existence of this unknown French drain system. <br /> New Item #205—Roadway Reconstruction Costs 33`d Ave. W to Sound Ave. The changed <br /> conditions encountered during pipe installation along Shore Avenue resulted in significant added width <br /> for trench patching and street restoration repairs. The City elected to have Shore Avenue restored from <br /> back of curb to back of curb. This cost pays for the removal and dump fees of the additional square <br /> yards of asphalt surfacing and existing asphalt curbing, the additional roadway excavation for a 7-inch <br /> thick roadway section comprising of 4-inches of crushed surfacing base course and 3-inches of HMA <br /> %2-inch PG 64-22, and the adjustment of various existing utility structures within the added foot print <br /> of the work. <br /> CONTRACT TIME: <br /> Fifteen, (15), additional working days are being added to the contract time as a result of this change <br /> order#2. <br /> Page 7 of 7 <br />