Project: Shore Avenue Storm Water Outfall Improvements Project <br /> Change Order No.2 <br /> Change Order Effective Date: May 11, 2016 <br /> Existing Item#60 - Crushed Surfacing Top Course. The use of crushed surfacing top course was <br /> deleted during street reconstruction and crushed surfacing base course was used instead. <br /> Existing Item#61 - Crushed Surfacing Base Course. Additional tons of crushed surfacing base <br /> course were used, in-lieu-of use of crushed surfacing top course, as the crushed surfacing base course <br /> provides a more structural roadway section. Additionally a full curb to curb street surfacing <br /> replacement approach,verses trench patching approach, resulted in the need of additional tons of <br /> crushed surfacing base course. <br /> Existing Item#62 -HMA Class 1/2-inch PG 64-22. Additional tons of HMA Class %2-inch PG 64-22 <br /> were used as a result of the full street restoration approach verses the trench patch approach. <br /> Existing Item#63 -Planing Bituminous Pavement. This bid item is being deleted as a result of the <br /> ground sloughing of the existing native soils during trench excavation, left minimal areas for planing <br /> of bituminous pavement. The planing of bituminous pavement which was completed on the project <br /> was paid for under the force account bid item. <br /> Existing Item#64 -Temporary Pavement Patch.No temporary pavement patching was completed <br /> during the course of this project. <br /> Existing Item#76—Gravel Borrow Including Haul. Additional tons of gravel borrow including <br /> haul were required to complete the trench backfilling due to the changed conditions encountered with <br /> sloughing soils and the need to remove these unsuitable soils during trench excavation and backfill. <br /> Existing Item#77 -Gravel Backfill for Foundations Class A. This bid item was not used during <br /> construction of the project. <br /> Existing Item#79 - Cleanout. This bid item was not used during construction of the project. <br /> Existing Item#82 -Extruded Cement Concrete Curb. This bid item was not used during <br /> construction of the project. <br /> New Item#201 —Costs for Initial Changed Conditions Notice. Between Lot No. 4 and 33rd Avenue <br /> West along Shore Avenue,the new storm trench followed alongside the existing sanitary sewer trench. <br /> The sanitary sewer trench was backfilled with unsuitable silty material, which when exposed to the <br /> unusual wet weather during the time of excavation to install new storm sewer, became unstable and <br /> sloughed into contractors storm sewer trench line, requiring it to be removed and replaced with new <br /> suitable gravel borrow material. This cost is to reimburse the contractor for the added labor and <br /> equipment costs to remove, load out, haul, and disposal of this unsuitable material. <br /> New Item #202—Additional Restoration Work,Lot 4 to 33rd Ave. W. This item pays for the <br /> installation of asphalt treated base material from City's Lot No. 4 to 33rd Ave West, demo of additional <br /> concrete and concrete curbs, demo of additional asphalt to approximate full roadway width, removal of <br /> additional spoils,prep of additional subgrade areas to receive asphalt treated base, replacement of <br /> existing damaged exposed aggregate concrete panels and driveway approaches and concrete curbs. <br /> Page 6 of 7 <br />