Laserfiche WebLink
1 <br /> 2 • Actual dimensions, arrangement, and materials used when different than shown in <br /> 3 the Plans. <br /> 4 • Changes made by Change Order or Field Order. <br /> 5 • Changes made by the Contractor. <br /> 6 • Accurate locations of storm sewer, sanitary sewer, water mains and other water <br /> 7 appurtenances, structures, conduits, light standards, vaults, width of roadways, <br /> 8 sidewalks, landscaping areas, building footprints, channelization and pavement <br /> 9 markings, etc. Include pipe invert elevations, top of castings (manholes, inlets, <br /> 10 etc.). <br /> 11 <br /> 12 If the Contract calls for the Contracting Agency to do all surveying and staking, the <br /> 13 Contracting Agency will provide the elevations at the tolerances the Contracting Agency <br /> 14 requires for the Record Drawings. <br /> 15 <br /> 16 When the Contract calls for the Contractor to do the surveying/staking, the applicable <br /> 17 tolerance limits include, but are not limited to the following: <br /> Vertical Horizontal <br /> As-built sanitary & storm invert and ± 0.01 foot ± 0.01 foot <br /> grate elevations <br /> As-built monumentation ± 0.001 foot ± 0.001 foot <br /> As-built waterlines, inverts, valves, ± 0.10 foot ± 0.10 foot <br /> hydrants <br /> As-built ponds/swales/water features ± 0.10 foot ± 0.10 foot <br /> As-built buildings (fin. Floor elev.) ± 0.01 foot ± 0.10 foot <br /> As-built gas lines, power, TV, Tel, Corn ± 0.10 foot ± 0.10 foot <br /> As-built signs, signals, etc. N/A ± 0.10 foot <br /> 18 <br /> 19 Making Entries on the Record Drawings: <br /> 20 <br /> 21 • Use erasable colored pencil (not ink) for all markings on the Record Drawings, <br /> 22 conforming to the following color code: <br /> 23 • Additions - Red <br /> 24 • Deletions - Green <br /> 25 • Comments - Blue <br /> 26 • Dimensions- Graphite <br /> 27 • Provide the applicable reference for all entries, such as the change order number, <br /> 28 the request for information (RFI) number, or the approved shop drawing number. <br /> 29 • Date all entries. <br /> 30 • Clearly identify all items in the entry with notes similar to those in the Contract <br /> 31 Drawings (such as pipe symbols, centerline elevations, materials, pipe joint <br /> 32 abbreviations, etc.). <br /> 33 <br /> 34 The Contractor shall certify on the Record Drawings that said drawings are an accurate <br /> 35 depiction of built conditions, and in conformance with the requirements detailed above. <br /> 36 The Contractor shall submit final Record Drawings to the Contracting Agency. <br /> 37 Contracting Agency acceptance of the Record Drawings is one of the requirements for <br /> 38 achieving Physical Completion. <br /> HAWTHORNE ELEMENTARY <br /> SAFE ROUTES TO SCHOOL <br /> FED AID#SRTS-0420(021); COE#3540 SP-22 March 16,2016 <br />