CITY OF EVERETT SPECIAL PROVISIONS <br /> Upon correction of all deficiencies, the Engineer will notifythe Contractor and the City, <br /> 9 Y <br /> in writing, of the date upon which the Work was considered physically complete. That <br /> date shall constitute the Physical Completion Date of the Contract, but shall not imply <br /> acceptance of the Work or that all the obligations of the Contractor under the Contract <br /> have been fulfilled. <br /> 1 1-05.11(3) Operational Testing <br /> It is the intent of the City to have at the Physical Completion Date a complete and <br /> operable system. Therefore when the Work involves the installation of machinery or <br /> other mechanical equipment; street lighting, electrical distribution or signal systems; <br /> irrigation systems; buildings; or other similar work it may be desirable for the Engineer <br /> to have the Contractor operate and test the Work for a period of time after final <br /> inspection but prior to the Physical Completion Date. Whenever items of Work are <br /> listed in the Contract Documents for operational testing they shall be fully tested under <br /> operating conditions for the time period specified to ensure their acceptability prior to <br /> the Physical Completion Date. During and following the test period, the Contractor <br /> shall correct any items of workmanship, materials, or Equipment that prove faulty, or <br /> that are not in first class operating condition. Equipment, electrical controls, meters, or <br /> other devices and Equipment to be tested during this period shall be tested under the <br /> observation of the Engineer, so that the Engineer may determine their suitability for the <br /> purpose for which they were installed. The Physical Completion Date cannot be <br /> established until testing and corrections have been completed to the satisfaction of the <br /> Engineer. <br /> The costs for power, gas, labor, material, supplies, and everything else needed to <br /> successfully complete operational testing, shall be included in the unit contract prices <br /> related to the system being tested, unless specifically set forth otherwise in the <br /> Proposal. <br /> 1 Operational and test periods, when required by the Engineer, shall not affect a <br /> manufacturer's guaranties or warranties furnished under the terms of the Contract. <br /> 1-05.12 Final Acceptance <br /> Delete all of 1-05.12 and substitute the following: <br /> The Contractor shall perform all the obligations under the Contract before the <br /> completion date can be established. A certificate of completion of the Work issued by <br /> the City will establish the completion date and certify the Work as complete. The <br /> following shall occur before the completion date can be established: <br /> The Final Contract Voucher Certification shall be signed by the Contractor verifying <br /> agreement to the final contract price. <br /> The physical work on the Project shall be complete. <br /> The Contractor shall furnish all documentation required by the Contract and required <br /> by law, necessary to allow the City to certify the Contract as complete. <br /> A certificate of completion for the Work, signed by the City, will constitute acceptance <br /> of the Work. The issuance of this certificate of completion will not constitute <br /> acceptance of unauthorized or defective Work, Equipment, or materials. <br /> The Contractor agrees that neither completion nor final acceptance shall relieve the <br /> Contractor of the responsibility to indemnify, defend, and protect the City against any <br /> claim or loss resulting from the failure of the Contractor, or the Subcontractors or lower <br /> tier subcontractors, to pay all laborers, mechanics, Subcontractors, material persons, <br /> SEWER SYSTEM REPLACEMENT AND CAPACITY IMPROVEMENTS SEWER "M" PHASE II <br /> WO No.- UP3470-10 Division 1 -GENERAL REQUIREMENTS April 2016 <br /> SP-87 <br /> I <br />