CITY OF EVERETT SPECIAL PROVISIONS <br /> Pre-existing unknown physical conditions at the site, of an unusual nature, <br /> differing materially from those ordinarily encountered and generally recognized as <br /> ' inhering in work of the character provided for in this Contract. <br /> If requested in writing by the Contractor and if the City's Representative finds that <br /> conditions are materially different and cause a material increase or decrease in the <br /> Contractor's cost of performance of the Work, or extends the duration of the critical <br /> path of the schedule, the City's Representative will make an adjustment of Contract <br /> Sum or Contract Time. Extensions of Contract Time will be evaluated in accordance <br /> with 1-08.3 PROGRESS SCHEDULE. <br /> However, if the parties are unable to agree on an adjustment of Contract Sum or <br /> Contract Time, the City's Representative will determine the amount of the adjustment <br /> of Contract Sum or Contract Time. If the City's Representative determines that <br /> differing site conditions do not exist or that no adjustment in Contract Sum or Contract <br /> Time is warranted, such determination shall be final. If there is a decrease in the cost <br /> or time required to perform the Work, failure of the Contractor to notify the City's <br /> Representative of the differing site condition shall not affect the City's right to make an <br /> adjustment in the Contract Sum or Contract Time. Additionally, no Contract Claim or <br /> adjustment of Contract Sum or Contract Time shall be allowed unless the Contractor <br /> has followed the procedures provided for in this Contract, including, but not limited to, <br /> furnishing timely Notice of the event and its effect on Contract Time and Contract Sum <br /> as required herein. <br /> 1-05 CONTROL OF WORK <br /> 1-05.1 Authority of the Engineer <br /> Delete 1-05.1 and substitute the following: <br /> 1-05.1 City <br /> The City, and the City's Representative, shall have the authority to act as the sole judge of <br /> the Work and materials with respect to both quantity and quality as set forth in the Contract. <br /> It is expressly stipulated that the Plans, Specifications and other Contract Documents set <br /> forth the requirements as to the nature of the completed Work and do not purport to control <br /> the method of performing Work except in those instances where the nature of the <br /> completed Work is dependent on the method of performance. <br /> The City has the authority to act, do, perform, and make all decisions and actions <br /> authorized by the Contract Documents, including, but not limited to, Change Orders, <br /> progress payments, contract decisions, acceptability of the Contractor's Work, and early <br /> possession. The City has the authority to accept or reject requests for progress payments <br /> that have been submitted by the Contractor and recommended by the City's <br /> Representative. The City has the authority to make determinations of the acceptability of <br /> the Work. The City also has the authority to accept or reject the City's Representative's <br /> recommendations regarding retention of defective Work. <br /> I <br /> I <br /> SEWER SYSTEM REPLACEMENT AND CAPACITY IMPROVEMENTS SEWER"M" PHASE II <br /> WO No.- UP3470-10 Division 1 -GENERAL REQUIREMENTS April 2016 <br /> SP-77 <br /> 1 <br />