Laserfiche WebLink
i <br /> CITY OF EVERETT PUBLIC WORKS DOCUMENT 00 72 13 , <br /> SPECIAL PROVISIONS GENERAL CONDITIONS <br /> 2) Resources , <br /> a) To demonstrate the Contractor could not and did not use resources, <br /> including but not limited to labor,materials and equipment from this Project <br /> for any other work on this or any other project during the period of delay <br /> (12.4.C.5.b.1)c).),the Contractor must: <br /> i) Affirmatively represent and warrant that it did not perform substitute <br /> Work; <br /> ii) Identify the specific resources that were idled; and <br /> iii)Show that those resources did not,and could not,work on other contracts <br /> or projects during the Delay. 111b) No Material Variations <br /> i) To demonstrate the Contractor's Overhead costs did not materially vary <br /> from its usual seasonal Overhead costs during the period of delay <br /> (12.4.C.5.b.1)d)),the Contractor must; <br /> ii) Affirmatively represent and warrant that the completion of the subject <br /> Work was extended and that such extension prevented the performance <br /> of other work during both the period of delay and the later period of time <br /> required to complete the extended Work, <br /> iii)Disclose the details of Contractor generated billings and Contractor <br /> Overhead Costs (as hereinafter defined) throughout the actual project <br /> performance. The details of such information should be no less than <br /> specific identification of the sources and amounts of revenue on no <br /> greater than a monthly basis and specific identification of the types and <br /> amounts of Contractor Overhead Costs on no greater than a monthly <br /> basis for the actual Project duration. <br /> c. Overabsorbed Overhead <br /> 1) To demonstrate that it did not incur Overabsorbed Overhead in the period <br /> following the Delay(12.4.C.5.b.1)e)),the Contractor must: <br /> a) Affirmatively represent and warrant that completion of the delayed Work <br /> prevented the performance of other work; <br /> b) Identify the critical resource unavailable for other work due to completion of <br /> the delayed Contract; and <br /> c) Showing that unavailability of this critical resource precluded the <br /> performance of other work. <br /> D. Inefficiencies <br /> 1. Adjustment of Contract Sum <br /> a. To the extent Contractor is entitled to an increase in Contract Sum because of <br /> inefficiencies or impaired productivity, then compensation due, if any, shall be <br /> calculated as provided in 9.5. Adjustment Of Contract Sum. <br /> 2. Adjustment of Contract Time <br /> a. To the extent Contractor is entitled to an extension of Contract Time because of <br /> inefficiencies or impaired productivity, then the time extension, if any, shall be <br /> determined as provided in 5.2.C. Extensions of Contract Time. <br /> 1 <br /> PSO6 REROUTE 007213 -60 <br /> WO NO.—UP3583 MAY 2016 <br /> 1 <br />