Laserfiche WebLink
CITY OF EVERETT PUBLIC WORKS DOCUMENT 00 72 13 <br /> SPECIAL PROVISIONS GENERAL CONDITIONS <br /> 1. If the Work has been wholly suspended pursuant to 5.3. Suspension Procedures for more <br /> than ninety(90)days as measured from the date of the notice to suspend,then the Contractor <br /> may terminate this Contract by providing Owner with ten (10) days' Notice that the <br /> ' Contractor shall deem the Contract to be terminated if the Owner does not provide <br /> Contractor with notice to resume Work within those ten(10)days. Such termination shall be <br /> treated as a termination for the Owner's convenience pursuant to 5.4.B Termination for <br /> Convenience. <br /> D. Contractor Obligations upon Termination <br /> 1. On receipt of notice of termination, the Contractor shall immediately discontinue the Work <br /> but shall do such Extra Work as may be ordered by the Owner's Representative or Owner to <br /> safeguard the Work then completed and the materials and Equipment then delivered to the <br /> Site of the Work and to leave the Work in a safe and useful condition. Payment for this <br /> Extra Work will be made in accordance with 9.2. Payment For Changes. <br /> E. Ownership of Materials upon Termination <br /> 1. As of the termination date, whether effected by the Owner or Contractor as provided herein, <br /> all the Contractor's right,title,and interest in and to materials ordered by the Contractor prior <br /> to termination, whether or not they have been delivered to the Site of Work, shall be vested <br /> in the Owner, and the Contractor shall, upon demand of the Owner, execute and deliver to <br /> the Owner all requisite bills of sale, assignments, and other documents of transfer that may <br /> be necessary to give effect to the intention of the termination procedures set forth above. <br /> ' F. Opportunity to Cure <br /> 1. If the Contractor has not already had an opportunity to cure the default or breach the Owner <br /> shall specify the default or breach and a reasonable period of time to allow the Contractor to <br /> cure the default or breach. The notice of termination will state the time period in which cure <br /> is permitted and other conditions as the Owner, in its sole judgment, shall deem appropriate. <br /> If Contractor fails to remedy the breach or default or any of the terms, covenants, or <br /> conditions of this Contract to the Owner's satisfaction within the time period specified or the <br /> Owner shall have the right to terminate the Contract without any further obligation to the <br /> Contractor. Any such termination for default shall not in any way operate to preclude the <br /> ' Owner from also pursuing all available remedies against Contractor and its sureties for said <br /> breach or default. <br /> G. Waiver of Remedies for Any Breach. <br /> 1. In the event that the Owner elects to waive its remedies for any breach by Contractor or any <br /> covenant, term or condition of this Contract, such waiver by the Owner shall not limit the <br /> ' Owner's remedies for any succeeding breach of that or of any other term covenant, or <br /> condition of this Contract. <br /> ' 5.5 Possession and Use of Completed Portions of the Work <br /> A. The Owner shall have the right to take possession of and use completed or partially completed <br /> portions of the Work even though the time for completing the Work for such portions may not <br /> ' have expired. Operations and maintenance costs of use of such Work will be borne by the <br /> Owner. Such possession and use shall not be deemed as acceptance of the Work. If such prior <br /> possession or use increases the cost of the Work, the Contractor may be entitled to request extra <br /> PS06 REROUTE 007213 -27 <br /> WO NO.—UP3583 MAY 2016 <br />