I <br /> CITY OF EVERETT SPECIAL PROVISIONS <br /> occur for Work until the entire Project is ready for possession and use. The <br /> acceptance Notice will include a Punch List of incomplete Work items and corrective <br /> Works, set the date for their completion and repair, describes the division of <br /> responsibility between the City and Contractor, and describe other terms of <br /> acceptance. The Contractor will acknowledge receipt of the acceptance Notice in <br /> writing. indicating acceptance of all of its terms and provisions. <br /> Subsequent to the Substantial Completion date, the City may exclude the Contractor <br /> from the Work during such periods when construction activities might interfere with the <br /> intended operation of the Project. The City, however, shall allow the Contractor <br /> reasonable access for completion or correction of incomplete Punch List items. <br /> 1-08.5(3) Acceptance of Work <br /> (******) <br /> Upon completion of the Project, including, but not limited to, record drawings, as-builts, <br /> required reports and operations and maintenance manuals, the Contractor shall so <br /> notify the City's Representative in writing. Upon receipt of the notification, the City's <br /> Representative will promptly, by personal inspection, determine the actual status of the <br /> Work in accordance with the terms of the Contract. If the City's Representative finds <br /> materials, Equipment, or workmanship that do not meet the terms of the Contract, it <br /> will prepare a Punch List of such items and submit it to the Contractor. Following <br /> completion of the corrective work by the Contractor, the City's Representative will <br /> notify the City that the Work has been completed in accordance with the Contract. The <br /> City shall make the final determination of acceptability and completion. For portions of <br /> the Project not previously accepted as substantially complete, the conditions of <br /> guarantee shall commence on the date that the City determines the Project is <br /> complete. <br /> 1-08.6 Suspension of Work <br /> Supplement 1-08.6 by adding the following: <br /> 1-08.6(1) Suspension Procedures <br /> The City may, at its convenience and at any time and without cause, suspend all or <br /> any part of the Work by notice in writing to the Contractor. The Contractor shall <br /> resume the Work within five (5) calendar days after receiving written notice from the <br /> City to do so. The Contractor will be allowed an increase in the Contract Sum or an <br /> extension of Contract Time, or both, directly attributable to any suspension in <br /> accordance with the Change Order procedures in these Special Provisions; provided, <br /> the Contractor shall not be entitled to any increase to the extent caused by the <br /> Contractor. <br /> 1-08.7 Maintenance During Suspension <br /> Delete all of 1-08.7 and substitute the following: <br /> Before and during any suspension (as described in Section 1-08.6) the Contractor <br /> shall protect the Work from damage or deterioration. Suspension shall not relieve the <br /> Contractor from anything the Contract requires unless this Section states otherwise. <br /> At no expense to the City, the Contractor shall provide through the construction area a <br /> safe, smooth, and unobstructed roadway, sidewalk, and path for public use during <br /> suspension, as required in 1-07.23 PUBLIC CONVENIENCE AND SAFETY. This may <br /> require a temporary road or detour. <br /> Water Main Replacement"Q" Division 1 -GENERAL CONDITIONS July 8, 2016 <br /> - Broadway <br /> WO No.-UP3612 SP -97 <br /> I <br />