i <br /> CITY OF EVERETT SPECIAL PROVISIONS <br /> Where asphalt concrete pavement overlays cement concrete pavement base, i <br /> saw cut in accordance with 2-02.3(6) Sawing and Line Drilling. <br /> 2-02.3(3)C Removal of Curb, Curb and Gutter <br /> Remove existing curbs where shown on the Plans or where encountered in the <br /> Work and designated by the Engineer. <br /> Existing curb and gutter includes, but is not limited to, cement concrete, cement <br /> concrete curb with a brick gutter and a cement concrete back, or other <br /> combinations of rigid materials. Remove the entire curb and gutter section, <br /> regardless of material composition. <br /> 2-02.3(3)C1 Sawcutting <br /> Make vertical full depth saw cut between existing curb or curb and gutter to <br /> remain and the portion to be removed. <br /> 2-02.3(3)D Removal of Cement Concrete Sidewalks <br /> Protect existing concrete walk that is to remain in place, from equipment damage <br /> by using planking or cover with rock free eight-inch thick blanket of excavated soil. <br /> Provide Engineer with proposed pavement breakers before use and do not begin <br /> breaking pavement without Engineer's approval of the pavement breakers. <br /> 2-02.3(3)D1 Sawcutting <br /> Make vertical full depth saw cut between existing cement concrete sidewalk <br /> to remain and the portion to be removed at the nearest scribe marks beyond <br /> the neat line limits, or to the nearest joint. 111 No diagonal cuts in sidewalk will be allowed unless otherwise indicated on the <br /> Plans or directed by the Engineer. <br /> 2-02.3(4) Abandon Pipe in-place <br /> (******) <br /> Plug pipe ends of pipes designated on Plans being abandoned in-place using <br /> commercial concrete. If designated on Plans, fill abandoned in-place pipe with <br /> Controlled Density Fill as specified in 2-09.3(1)E. <br /> 2-02.3(6) Sawing and Line Drilling <br /> (******) <br /> Saw-cut to full depth mortared decorative or special pavement including, but not limited <br /> to, brick, cobblestone or paver block along a neat line with intent of salvaging as many <br /> units as possible. <br /> When line drilling, drill holes at maximum center-to-center spacing of six-inches. Drill <br /> holes perpendicular to the surface and penetrate completely through the pavement. <br /> When the Plans indicate, or the Engineer requires, saw-cutting pavement that is <br /> comprised of a rigid base and asphalt overlay, saw cut the rigid base to the minimum <br /> depth as follows: <br /> a. For concrete rigid base, saw cut to a depth of 2/3 the thickness of the rigid <br /> base. <br /> b. For rigid base constructed with mortared decorative or special pavement <br /> including, but not limited to, brick, cobblestone, or paver block, or a <br /> combination of such materials saw cut to full depth of the rigid base along a <br /> neat line with intent to salvage as many special pavement units as possible. <br /> Water Main Replacement"Q" Division 2-EARTHWORK July 8, 2016 <br /> -Broadway <br /> WO No.—UP3612 SP-130 <br />