Laserfiche WebLink
I <br /> I1 <br /> 2 1. Verify the primary horizontal and vertical control furnished by the Contracting <br /> I <br /> 3 Agency, and expand into secondary control by adding stakes and hubs as well <br /> 4 as additional survey control needed for the project. Provide descriptions of <br /> 5 secondary control to the Contracting Agency. The description shall include <br /> I <br /> 6 coordinates and elevations of all secondary control points. <br /> 7 <br /> 8 2. Establish, the centerlines of all alignments, by placing hubs, stakes, or marks <br /> I 9 on centerline or on offsets to centerline at all curve points (PCs, PTs, and Pls) <br /> 10 and at points on the alignments spaced no further than 50 feet. <br /> 11 <br /> 12 3. Establish clearing limits, placing stakes at all angle points and at intermediate <br /> I13 points not more than 50 feet apart. The clearing and grubbing limits shall be 5 <br /> 14 feet beyond the toe of a fill and 10 feet beyond the top of a cut unless <br /> 15 otherwise shown in the Plans. <br /> I 16 <br /> 17 4. Establish grading limits, placing slope stakes at centerline increments not <br /> 18 more than 50 feet apart. Establish offset reference to all slope stakes. If <br /> I 19 Global Positioning Satellite (GPS) Machine Controls are used to provide grade <br /> 20 control, then slope stakes may be omitted at the discretion of the Contractor <br /> 21 <br /> I <br /> 22 <br /> 23 5. Establish the horizontal and vertical location of all drainage features, placing <br /> offset stakes to all drainage structures and to pipes at a horizontal interval not <br /> 24 greater than 25 feet. <br /> I 25 <br /> 26 6. Establish roadbed and surfacing elevations by placing stakes at the top of <br /> 27 subgrade and at the top of each course of surfacing. Subgrade and surfacing <br /> 28 stakes shall be set at horizontal intervals not greater than 50 feet in tangent <br /> I <br /> 29 sections, 25 feet in curve sections with a radius less than 300 feet, and at 10- <br /> 30 foot intervals in intersection radii with a radius less than 10 feet. Transversely, <br /> 31 stakes shall be placed at all locations where the roadway slope changes and <br /> I <br /> 32 at additional points such that the transverse spacing of stakes is not more than <br /> 33 12 feet. If GPS Machine Controls are used to provide grade control, then <br /> 34 roadbed and surfacing stakes may be omitted at the discretion of the <br /> I 35 Contractor. <br /> 36 <br /> 37 7. Establish intermediate elevation benchmarks as needed to check work <br /> I 38 throughout the project. <br /> 39 <br /> 40 8. Provide references for paving pins at 25-foot intervals or provide simultaneous <br /> I 41 surveying to establish location and elevation of paving pins as they are being <br /> 42 placed. <br /> 43 <br /> 44 9. For all other types of construction included in this provision, (including but not <br /> I <br /> 45 limited to channelization and pavement marking, illumination and signals, <br /> 46 guardrails and barriers, and signing) provide staking and layout as necessary <br /> 47 to adequately locate, construct, and check the specific construction activity. <br /> I 48 <br /> 49 10. Contractor shall determine if changes are needed to the profiles or roadway <br /> 50 sections shown in the Contract Plans in order to achieve proper smoothness <br /> I51 and drainage where matching into existing features, such as a smooth <br /> I PACIFIC&BROADWAY SAFETY IMPROVEMENTS <br /> FED AID#HSIP-0005(331); COE#3523 <br /> CITYWIDE SAFETY IMPROVEMENTS <br /> FED AID#HSIP-0005(330); COE#3524 13 December 23,2015 <br />