Project: East Grand Ave Sewer System Replacement and Storm Water Separation <br /> Change Order No. 3 <br /> Change Order Effective Date: November 8, 2016 <br /> CONTRACTOR <br /> By f .)-_ t Date: ( 1 / N l( <br /> ll Officer <br /> Exhibit A—Description of Changed Work <br /> Change order#3 modifies two existing bid items and adds four(4)new items to Schedule B of the <br /> contract as follows: <br /> Under Schedule B of the Proposal: <br /> Modified Bid Items: <br /> Modify existing bid item B-14 titled, "Control Density Fill",by deleting 452 cubic yards of control <br /> density fill at the unit rate of$110.00 per cubic yard,resulting in a$49,720.00 decrease to the contract <br /> price. <br /> Modify existing bid item B-58 titled, "Remove& Replace Generator Pad" at the lump sum price of <br /> $18,000.00,resulting in a$18,000.00 decrease to the contract price. <br /> New Items: <br /> Add new item B-66 titled, "Pervious Concrete" to the contract by adding 590 square yards of <br /> pervious concrete at the unit rate of$85.00/square yard,resulting in a$50,150.00 contract price <br /> increase. <br /> Add new item B-67 titled, "Private Walkways"to the contract by adding 18 square yards of private <br /> walkways at the unit rate of$205.00/square yard, resulting in a$3,690.00 contract price increase. <br /> Add new item B-68 titled, "Concrete Steps"to the contract by adding 8 each concrete steps at the <br /> unit rate of$255.00/each,resulting in a$2,040.00 contract price increase. <br /> Add new item B-69 titled, "Remove & Replace Generator Pad"to the contract at the new revised <br /> lump sum price of$10,000.00. <br /> Net result of modifying two (2) existing bid items and adding four(4)new items to Schedule B of the <br /> contract,results in$1,840.00 contract price decrease. <br /> Page 3 of 4 <br />