Project: East Grand Ave Sewer System Replacement and Storm Water Separation <br /> Change Order No. 3 <br /> Change Order Effective Date: November 8,2016 <br /> JUSTIFICATION: <br /> Schedule B: <br /> Modified Bid Items: <br /> Bid Item B-14- Control Density Fill. The quantity of control density fill was not required nearly to <br /> the extent anticipated during the design and allowed for in the bid proposal. <br /> Bid Item B-58- Remove& Replace Generator Pad. This bid item is being deleted as a result of the <br /> added work at Lift Station#32. A portion of the work required under this bid item was done by City of <br /> Everett forces and the rest of the work was completed by KLB Construction forces. The revised work <br /> effort required by KLB Construction is being paid under new bid item B-69—Remove&Replace <br /> Generator Pad. <br /> New Items: <br /> Item B-66—Pervious Concrete. At the intersections of 21St, 22nd, 23rd and 24th Streets and East <br /> Grand Avenue,where curb bulb-outs were added to make space for the new Stormwater treatment <br /> units,pervious concrete is being used in these areas between the sidewalk and new curb. This is in lieu <br /> of topsoil and grass which would become a maintenance burden for the City or adjacent property <br /> owners. Pervious concrete is expected to require very little maintenance and is consistent with the <br /> objectives of this project which is to reduce storm water runoff in the sewer system. The cost for <br /> pervious concrete includes the removal of existing materials to a depth of 1 foot, and placement of 4- <br /> inches of pervious concrete over 8-inches of free draining gravel. <br /> Item B-67—Private Walkways and item B-68—Concrete Steps. Justification for these two items <br /> was necessary as the new curb and sidewalk grade elevations changed slightly along various areas of <br /> East Grand Avenue,requiring height adjustments to the private walkways that abut the new sidewalk <br /> grade. In certain instances new concrete steps were incorporated into these private walkways to aid in <br /> matching grade of new sidewalks. <br /> Item B-69—Remove& Replace Generator Pad. This bid item is being added as portion of the work <br /> required under original bid item#58 was completed by City of Everett forces,with the rest of the work <br /> completed by KLB Construction forces. The revised work effort required by KLB Construction is paid <br /> for under this new bid item. <br /> CONTRACT TIME: <br /> Twenty eight(28)working days are being added to the contract time by change order#3 as a result of <br /> structural modifications made to Lift Station#32 to raise the height of the existing wet well structure. <br /> The hatchways requested by the City's Technical Service Group, in the top concrete slab above the wet <br /> well of the lift station, had significant long lead procurement time frames, which resulted in the need to <br /> add these additional 28 working days. <br /> Page 4 of 4 <br />