Laserfiche WebLink
• <br /> ii <br /> Project:Combned Sewer Improvement"D" <br /> Change Order No. 1 <br /> Change Order Effective Date:2/24/03 <br /> Contractor and City agree as follows: <br /> 1. The Scope of Work shall be changed to the extent described in Exhibit A. <br /> 2. In full and complete compensation for the changes described in Exhibit A,including all direct <br /> and indirect costs and impacts,the contract price shall be adjusted as described in this Change <br /> Order. <br /> 3. The duration of the Contract shall be adjusted to the extent described in this Change Order. <br /> 4. Contractor waives and releases any and all claims arising out of,or related to,this Change <br /> Order,the work described in Exhibit A, and all work and actual or constructive changes that <br /> occurred or began prior to the date of this Change Order,including,but not limited to,claims <br /> for equitable adjustment of time and compensation,delay,impact,overhead,or inefficiencies; <br /> provided,however,that any claims previously submitted by the Contractor to the City in <br /> accordance with contract requirements that have not been resolved by mutual agreement as of <br /> the date of Contractor's signing of this Change Order remain outstanding and are not waived <br /> or released by this Change Order. <br /> 5. This Change Order only changes the contract between Contractor and City to the extent <br /> explicitly provided herein. <br /> CITY <br /> Attest- Approved As to Foran: <br /> Mayor City Clerk City Attorney <br /> Date: Date: Date: <br /> Recommended By: <br /> Construction Project Engineer (if Engineering Department Director <br /> Manager(if applicable) Manager(if <br /> applicable) a.plicable) <br /> Aft <br /> D. e: /6/e,5 Date: 3 /1' • te: W2/o3 Date: '0 <br /> CONTRACTOR <br /> � n <br /> 13 t <br /> A.L. in , Date: <br /> MAR 0 4 2003 <br /> Officer <br /> tj 'f <br /> Page 2 of 3 <br />