Project:Combined Sewer Improvements"D" 11111.111.1)1101, <br /> Change Order No.2 <br /> Change Order Effective Date: 8/15/2003 <br /> Item#33—Adjust Catch Basin to Grade. Since two catch basins were added during field modifications. <br /> there was an increase in the number of adjustments required. <br /> Item#34—Force Account. The original estimated Force Account was not needed during construction <br /> which resulted in a decrease to the contract. <br /> Item#35—Drop Manhole. An additional drop manhole connection was not accounted for in the original <br /> estimate. <br /> Item#36—Extruded Asphalt Curb and Driveway Berms. The City opted to install an extruded asphalt <br /> curb and berm in lieu of using Item#27 for a concrete extruded curb. City crews are better able to repair <br /> and maintain the asphalt curb and berms: <br /> Item#37—Removal and Replacement of Sidewalk. This item was added to replace a portion of the <br /> quantities for Item#8 associated with the East Marine View Drive sewer installation. The contractor was <br /> able to retain the concrete curb and gutter along this portion of the project. <br /> Item#38—Crossing of East Marine View Drive. The City approved a Cost Reduction Incentive <br /> Proposal(CRIP)from the contractor to install the sewer crossing of East Marine View Drive using a <br /> trenchless method and to install the pipe alignment along East Marine View Drive in the current sidewalk. <br /> Other items show a reduction for quantities not used. This items pays for the installation,Item#41 <br /> designates the contractor's share of the savings. <br /> Item#40—Equitable Adjustment to Bid Item#12. As stated in Item#12 the contractor was entitled to <br /> an equitable adjustment for side sewer connections per WSDOT Specifications Section 1-04.6 Increased or <br /> Decreased Quantities. <br /> Item#41—CRIP Savings. A Cost Reduction Incentive Proposal(CRIP)involves a 50/50 split of the <br /> resulting savings from using the contractor's proposal. This item allots the contractor half of the savings <br /> for using Item#38. <br /> • <br /> C. Additional Contract Time <br /> The City will add an additional 17 working days to the contract for miscellaneous additional work,side <br /> sewer exploration,and completion of punchlist items. <br /> • <br /> Exhibit A <br /> Page 5 of 5 <br />