Laserfiche WebLink
7 <br /> Mr.Kim Buike <br /> 06 January 2006 <br /> Page 5 <br /> Preliminary Schedule Estimate: <br /> A. Parking Area Task 1: Parking Area Drawings 3-4 weeks <br /> B. Park Task 1: 30% Park Drawings 4—5 weeks <br /> B. Park Task 2: 60%Park Drawings, Specifications, & Cost Estimate 7—9 weeks <br /> B. Park Task 3: 90%Park Drawings,Specifications, & Cost Estimate 6— 8 weeks <br /> B. Park Task 4: Final Park Engineering& Design Construction Documents 3—4 weeks <br /> B. Park Task 5: Flagpole Relocation 4—5 weeks <br /> B. Park Task 6: Existing Shoreline Assessment 2—3 weeks <br /> B. Park Task 7: Shoreline Permit 6—8 weeks <br /> We are very excited about working with you on this park again. If you have any adjustments to our scope of work <br /> and fees, please call. <br /> Best regards, <br /> HOUGH BECK & BAIRD INC. <br /> Colie Hough-Beck, ASLA Dean W.Koonts,ASLA <br /> President Associate <br /> Attachments: <br /> 1) Exhibit 1: Marine Park Improvements <br /> 2) PND Letter dated January 5,2005 <br /> 31 <br />