Marshbank Construction 1/25/2017 Change Order 1
>
Contracts
>
Capital Contract
>
Marshbank Construction 1/25/2017 Change Order 1
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
3/7/2017 1:42:22 PM
Creation date
3/7/2017 1:42:19 PM
Metadata
Fields
Template:
Contracts
Contractor's Name
Marshbank Construction
Approval Date
1/25/2017
Department
Public Works
Department Project Manager
Grace Kane
Subject / Project Title
41st St to W. Marine View Dr. Corridor Impvts
Amendment/Change Order
Change Order
Amendment/Change Order Number
1
Tracking Number
0000049
Total Compensation
$125,608.53
Contract Type
Capital Contract
Retention Period
10 Years Then Transfer to State Archivist
Document Relationships
Marshbank Construction 5/9/2016
(Amendment)
Path:
\Documents\City Clerk\Contracts\Capital Contract
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
5
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
Project: 41St St to WMVD Freight Corridor Improvements <br /> Change Order No.1 <br /> Change Order Effective Date: December 19, 2016 <br /> Bid Item # 72—Uniformed Police Officer. Add new force account bid item# 72 entitled, <br /> "Uniformed Police Officer" for intersection control work, by adding $75,000.00 to this force account <br /> bid item, resulting in a$75,000.00 increase to the Contract price. <br /> Bid Item# 73—Class 4,000 Cement Concrete Sidewalk, 6-Inches Thick. Add new bid item# 73 <br /> entitled, "Class 4,000 Cement Concrete Sidewalk, 6-Inches Thick" at the agreed to unit price of <br /> $54.83/SY, by adding 75 square yards of Class 4,000 Cement Concrete Sidewalk, 6-Inches Thick to <br /> the Contract, resulting in a$4,112.25 increase to the Contract price. <br /> Bid Item # 74—Type E2 Cement Concrete Curb,3-Day Mix. Add new bid item# 74 entitled, <br /> "Type E2 Cement Concrete Curb, 3-Day Mix" at the agreed to unit price of$31.64/LF, by adding 115 <br /> linear feet of E2 Cement Concrete Curb, 3-Day Mix to the Contract, resulting in a$3,638.60 increase <br /> to the Contract price. <br /> Bid Item# 75—Class 4,000 Cement Concrete Curb & Gutter, Type A-1. Add new bid item# 75 <br /> entitled, "Class 4,000 Cement Concrete Curb & Gutter, Type A-1" at the agreed to unit price of <br /> $31.85/LF, by adding 200 linear feet of Class 4,000 Cement concrete Curb & Gutter to the Contract, <br /> resulting in a$6,370.00 increase to the Contract price. <br /> Bid Item # 76—42-Inch Black Polyvinyl Chain Link Fence. Add new bid item# 76 entitled, "42- <br /> Inch Black Polyvinyl Chain Link Fence" at the agreed to unit price of$48.75/LF, by adding 90 linear <br /> feet of 42-Inch Black Polyvinyl Chain Link Fence to the Contract, resulting in a$4,387.50 increase to <br /> the Contract price. <br /> JUSTIFICATION <br /> Bid Item #61 —Force Account Lean Concrete. This bid item is being deleted because lean concrete <br /> will not be used on this project. <br /> Bid Item # 68—Force Account Controlled Density Fill. This new bid item is being added to <br /> account for costs needed to pay for controlled density fill; dry or wet CDF may be used. This change <br /> order also adds the CDF Specification in the City of Everett Design and Construction Standards, <br /> section 3-20.1 to use for materials acceptance. <br /> Bid Item # 69—GarretCom Ethernet Switch. The Contract required the Contractor to provide the <br /> GarretCom Switches but did not provide a method of payment to the Contractor. This new bid item is <br /> being added to pay for Contractor provided GarretCom Ethernet Switches for this project. <br /> Bid Item # 70—CCTV Camera Replacement Cost Difference. The CCTV cameras listed in the <br /> Contract are no longer available and are being replaced with a camera that is available and is closest to <br /> the original model. This new bid item is being added to account for additional costs for replacement <br /> cameras. <br /> Page 4 of 5 <br />