Laserfiche WebLink
Project: 41st St to WMVD Freight Corridor Improvements <br /> Change Order No.1 <br /> Change Order Effective Date: December 19, 2016 <br /> Bid Item # 71 —Additional Traffic Loop Stubout Work. This new bid item is being added to pay <br /> for costs for additional electrical loop conduit work to house larger diameter wire that was not included <br /> in Contract. <br /> Bid Item # 72—Uniformed Police Officer. Intersection work requires that a uniformed police officer <br /> be present in the intersection to control traffic. There was not a bid item in the Contract to pay for this <br /> work, so this new bid item is being added to pay for costs to provide uniformed police officers for <br /> intersection control. <br /> Bid Item# 73—Class 4,000 Cement Concrete Sidewalk, 6-Inches Thick. This new bid item is <br /> being added to pay for costs to install higher strength concrete sidewalk in areas where heavy trucks <br /> frequently drive over sidewalk while turning. <br /> Bid Item # 74—Type E2 Cement Concrete Curb,3-Day Mix. This new bid item is being added to <br /> pay for costs to install E2 Curb in areas where curb and gutter is not needed, and was not included in <br /> the Contract. <br /> Bid Item # 75—Class 4,000 Cement Concrete Curb & Gutter, Type A-1. This new bid item is <br /> being added to pay for costs to install higher strength concrete curb & gutter in areas where heavy <br /> trucks frequently drive over curb while turning. <br /> Bid Item # 76—Black Polyvinyl Chain Link Fence. This new bid item is being added to pay for <br /> costs to install a fence behind the modular block wall that was installed as part of this Contract, and <br /> there was no corresponding bid item in the Contract to pay for the work. This fence is a safety <br /> requirement to ensure there is fall protection for entire length of wall. <br /> Contract Time: Twenty-five (25)working days are added to the Contract time as a result of <br /> Change Order# 1 as detailed below. <br /> 1. 5 working days added for additional loop and conduit work. <br /> 2. 5 working days added for acquiring and installing new cameras and additional electrical <br /> switches. <br /> 3. 5 working days added to acquire, manufacture made in USA fence material and to install <br /> fence. <br /> 4. 10 working days added to allow for time for private contractor to relocate gas station sign <br /> out of newly acquired City of Everett right of way and install in gas station property. <br /> Page 5 of 5 <br />