Project: WPCF Expansion Phase A <br /> Change Order No. 2 <br /> Change Order Effective Date: 5-3-07 <br /> Mme' 1 h 474 <br /> • <br /> By Date: 707 <br /> Officer <br /> Exhibit A—Description of Changed Work <br /> The change of work identified by this change order is an extension of time to the contract. It <br /> does not change the contract cost. Continuing problems with the Liquid V-notch weirs <br /> (LVN's), used to control the rate of injection of sodium hypochlorite, resulted in a change <br /> out of the LVN's to metering pumps. The time needed to supply, install, and commission <br /> the metering pumps exceeded the contract time by 43 calendar days. <br />